Commissioning Procedures for HVAC Engineers
Commissioning Procedures for HVAC Engineers
Commissioning (Cx) verifies HVAC systems meet design intent and owner’s project requirements through systematic functional performance testing. Proper commissioning reduces energy consumption by 10-20% and minimizes occupant complaints.
Commissioning Process
graph TD
A[Pre-Design Phase] --> B[Design Phase]
B --> C[Construction Phase]
C --> D[Acceptance Phase]
D --> E[Post-Acceptance Phase]
A --> A1[OPR Development]
B --> B1[Basis of Design]
B --> B2[Design Review]
C --> C1[Submittal Review]
C --> C2[Installation Verification]
D --> D1[Functional Testing]
D --> D2[TAB Verification]
D --> D3[Systems Manual]
E --> E1[Training]
E --> E2[Seasonal Testing]
E --> E3[10-Month Review]
Commissioning phases:
- Pre-design: Develop Owner’s Project Requirements (OPR)
- Design: Create Basis of Design (BOD), review submittals
- Construction: Verify installation, review submittals
- Acceptance: Functional performance testing
- Post-acceptance: Training, seasonal testing, warranty review
Owner’s Project Requirements (OPR)
Documents owner’s expectations:
- Indoor environmental quality (temperature, humidity, IAQ)
- Energy performance targets
- Maintenance requirements
- Special requirements (cleanrooms, labs, etc.)
- Budget and schedule constraints
Example OPR requirements:
- “Maintain operating room at 68-73°F, 20-60% RH, +0.01 "w.g. pressure”
- “Achieve LEED Gold certification with 30% energy cost savings”
- “Design system for 24/7 operation with N+1 redundancy”
Basis of Design (BOD)
Engineer’s documentation of how OPR will be met:
- System descriptions
- Design parameters and assumptions
- Equipment specifications
- Control sequences
- Maintenance requirements
Links OPR to design decisions
Functional Performance Testing
Verifies equipment operates per design intent under actual and simulated conditions
Test Categories
1. Pre-functional checklists:
- Verify installation completeness
- Check nameplate data vs. submittals
- Confirm startup procedures completed
- Document deficiencies
2. Functional performance tests:
- Test control sequences
- Verify safeties and interlocks
- Simulate failure modes
- Measure performance at design conditions
Example: AHU Functional Test
Test sequence:
Economizer test:
- Simulate OA temp < RA temp → OA damper opens to 100%
- Simulate OA temp > RA temp → OA damper returns to minimum
Heating sequence:
- Lower space temp setpoint → verify heating valve opens
- Verify discharge air temp maintains setpoint
- Check freeze protection (DA temp < 40°F → alarm)
Cooling sequence:
- Raise space temp setpoint → verify cooling valve opens
- Verify discharge air temp maintains setpoint
- Check high-limit safety (DA temp < 50°F → cooling lockout)
Ventilation:
- Verify minimum OA damper position (per ASHRAE 62.1)
- Measure actual OA flow with pitot traverse
- Check CO₂-based DCV if applicable
Alarms and safeties:
- Simulate dirty filter (increase DP) → verify alarm
- Simulate fan failure → verify alarm and backup fan start
- Simulate freeze condition → verify shutdown
Worked Example 1: VAV Box Functional Test
Test: Verify VAV terminal unit responds correctly to thermostat
Given:
- Design airflow: 1,200 CFM max, 360 CFM min (30%)
- Space setpoint: 72°F
- Reheat coil valve
Test Procedure:
Step 1: Verify minimum airflow
- Set space temp to 65°F (call for heat)
- Measure airflow with flow hood
- Expected: 360 CFM ±10%
- Result: 355 CFM → PASS
Step 2: Verify maximum cooling airflow
- Set space temp to 80°F (call for cooling)
- Expected: Airflow increases to 1,200 CFM before reheat
- Result: 1,180 CFM → PASS
Step 3: Verify reheat operation
- Maintain space at 80°F, increase setpoint to 72°F
- Expected: Airflow reduces to minimum, reheat valve opens
- Measure discharge air temp increase
- Result: Airflow 360 CFM, DA temp 95°F → PASS
Step 4: Verify deadband
- Set space temp = setpoint (72°F)
- Expected: Airflow at minimum, no heating or cooling
- Result: 360 CFM, reheat closed → PASS
Conclusion: VAV terminal operates per sequence
TAB Verification
Commissioning agent verifies TAB contractor work:
- Review TAB plan: Methodology, instruments, tolerances
- Witness testing: Observe 10-20% of measurements
- Review reports: Check calculations, balance tolerances
- Spot-check: Re-measure 5-10% of points independently
Acceptance criteria:
- Airflow: ±10% of design
- Hydronic flow: ±10% of design
- Temperature: ±2°F of setpoint
- Pressure: ±0.02 "w.g. of setpoint
Controls Verification
Verify BAS trends and sequences:
Trend setup:
- Sample rate: 15-minute intervals minimum
- Duration: 48-72 hours (capture occupied/unoccupied cycles)
- Points: Supply/return temps, damper positions, valve positions, fan status
Trend analysis:
- Check control stability (hunting, oscillation)
- Verify setpoints match design
- Confirm reset schedules active
- Identify simultaneous heating/cooling
Common issues found:
- PID tuning too aggressive (oscillation)
- Economizer not enabled
- Night setback not programmed
- Outdoor air damper stuck
Seasonal Testing
Some systems require testing outside of construction season:
- Heating: Test in winter (or simulate low OA temp)
- Cooling: Test in summer (or simulate high OA temp)
- Free cooling: Test economizer at shoulder season conditions
Deferred testing: Schedule within first year of operation
Issues Log and Deficiency Tracking
Maintain master issues log:
| Issue # | System | Description | Priority | Responsible | Status | Resolution |
|---|---|---|---|---|---|---|
| CX-001 | AHU-1 | Economizer damper stuck at minimum | High | Contractor | Closed | Actuator replaced 5/12 |
| CX-002 | VAV-205 | Airflow 20% below design | Medium | TAB | Open | Damper adjustment scheduled |
Priority levels:
- Critical: Life safety, code violation
- High: Significant energy waste, comfort impact
- Medium: Minor performance issue
- Low: Documentation, cosmetic
Systems Manual
Deliverable to owner:
- Design narrative: System descriptions, design basis
- Equipment documentation: O&M manuals, shop drawings, warranties
- Control sequences: Detailed written sequences with points list
- As-built drawings: Red-lined to reflect actual installation
- TAB reports: Final airflow and water flow measurements
- Functional test reports: Results of all Cx tests
- Training documentation: Training session materials, video recordings
Training
Provide to facilities staff:
- Systems overview: How each system operates
- Operator interface training: BAS navigation, override procedures
- Preventive maintenance: Filter changes, belt inspections, seasonal tasks
- Troubleshooting: Common problems and solutions
Training sessions:
- Minimum 4 hours for complex systems
- Hands-on demonstrations
- Provide training manual
- Record sessions for future staff
Practical Applications
- New construction: Full commissioning per ASHRAE Guideline 0
- Existing buildings: Retro-commissioning (RCx) identifies 5-15% energy savings
- LEED: Enhanced commissioning (EAc3) requires additional testing
- Code compliance: Some jurisdictions require commissioning (California Title 24)
Related Technical Guides:
References:
- ASHRAE Guideline 0: The Commissioning Process
- ASHRAE Guideline 1.1: HVAC&R Technical Requirements for the Commissioning Process
- ASHRAE Standard 202: Commissioning Process for Buildings and Systems
- NEBB Procedural Standards for Building Systems Commissioning