HVAC Systems Encyclopedia

A comprehensive encyclopedia of heating, ventilation, and air conditioning systems

Commissioning Procedures for HVAC Engineers

Commissioning Procedures for HVAC Engineers

Commissioning (Cx) verifies HVAC systems meet design intent and owner’s project requirements through systematic functional performance testing. Proper commissioning reduces energy consumption by 10-20% and minimizes occupant complaints.

Commissioning Process

graph TD
    A[Pre-Design Phase] --> B[Design Phase]
    B --> C[Construction Phase]
    C --> D[Acceptance Phase]
    D --> E[Post-Acceptance Phase]
    
    A --> A1[OPR Development]
    B --> B1[Basis of Design]
    B --> B2[Design Review]
    C --> C1[Submittal Review]
    C --> C2[Installation Verification]
    D --> D1[Functional Testing]
    D --> D2[TAB Verification]
    D --> D3[Systems Manual]
    E --> E1[Training]
    E --> E2[Seasonal Testing]
    E --> E3[10-Month Review]

Commissioning phases:

  1. Pre-design: Develop Owner’s Project Requirements (OPR)
  2. Design: Create Basis of Design (BOD), review submittals
  3. Construction: Verify installation, review submittals
  4. Acceptance: Functional performance testing
  5. Post-acceptance: Training, seasonal testing, warranty review

Owner’s Project Requirements (OPR)

Documents owner’s expectations:

  • Indoor environmental quality (temperature, humidity, IAQ)
  • Energy performance targets
  • Maintenance requirements
  • Special requirements (cleanrooms, labs, etc.)
  • Budget and schedule constraints

Example OPR requirements:

  • “Maintain operating room at 68-73°F, 20-60% RH, +0.01 "w.g. pressure”
  • “Achieve LEED Gold certification with 30% energy cost savings”
  • “Design system for 24/7 operation with N+1 redundancy”

Basis of Design (BOD)

Engineer’s documentation of how OPR will be met:

  • System descriptions
  • Design parameters and assumptions
  • Equipment specifications
  • Control sequences
  • Maintenance requirements

Links OPR to design decisions

Functional Performance Testing

Verifies equipment operates per design intent under actual and simulated conditions

Test Categories

1. Pre-functional checklists:

  • Verify installation completeness
  • Check nameplate data vs. submittals
  • Confirm startup procedures completed
  • Document deficiencies

2. Functional performance tests:

  • Test control sequences
  • Verify safeties and interlocks
  • Simulate failure modes
  • Measure performance at design conditions

Example: AHU Functional Test

Test sequence:

  1. Economizer test:

    • Simulate OA temp < RA temp → OA damper opens to 100%
    • Simulate OA temp > RA temp → OA damper returns to minimum
  2. Heating sequence:

    • Lower space temp setpoint → verify heating valve opens
    • Verify discharge air temp maintains setpoint
    • Check freeze protection (DA temp < 40°F → alarm)
  3. Cooling sequence:

    • Raise space temp setpoint → verify cooling valve opens
    • Verify discharge air temp maintains setpoint
    • Check high-limit safety (DA temp < 50°F → cooling lockout)
  4. Ventilation:

    • Verify minimum OA damper position (per ASHRAE 62.1)
    • Measure actual OA flow with pitot traverse
    • Check CO₂-based DCV if applicable
  5. Alarms and safeties:

    • Simulate dirty filter (increase DP) → verify alarm
    • Simulate fan failure → verify alarm and backup fan start
    • Simulate freeze condition → verify shutdown

Worked Example 1: VAV Box Functional Test

Test: Verify VAV terminal unit responds correctly to thermostat

Given:

  • Design airflow: 1,200 CFM max, 360 CFM min (30%)
  • Space setpoint: 72°F
  • Reheat coil valve

Test Procedure:

Step 1: Verify minimum airflow

  • Set space temp to 65°F (call for heat)
  • Measure airflow with flow hood
  • Expected: 360 CFM ±10%
  • Result: 355 CFM → PASS

Step 2: Verify maximum cooling airflow

  • Set space temp to 80°F (call for cooling)
  • Expected: Airflow increases to 1,200 CFM before reheat
  • Result: 1,180 CFM → PASS

Step 3: Verify reheat operation

  • Maintain space at 80°F, increase setpoint to 72°F
  • Expected: Airflow reduces to minimum, reheat valve opens
  • Measure discharge air temp increase
  • Result: Airflow 360 CFM, DA temp 95°F → PASS

Step 4: Verify deadband

  • Set space temp = setpoint (72°F)
  • Expected: Airflow at minimum, no heating or cooling
  • Result: 360 CFM, reheat closed → PASS

Conclusion: VAV terminal operates per sequence

TAB Verification

Commissioning agent verifies TAB contractor work:

  1. Review TAB plan: Methodology, instruments, tolerances
  2. Witness testing: Observe 10-20% of measurements
  3. Review reports: Check calculations, balance tolerances
  4. Spot-check: Re-measure 5-10% of points independently

Acceptance criteria:

  • Airflow: ±10% of design
  • Hydronic flow: ±10% of design
  • Temperature: ±2°F of setpoint
  • Pressure: ±0.02 "w.g. of setpoint

Controls Verification

Verify BAS trends and sequences:

  1. Trend setup:

    • Sample rate: 15-minute intervals minimum
    • Duration: 48-72 hours (capture occupied/unoccupied cycles)
    • Points: Supply/return temps, damper positions, valve positions, fan status
  2. Trend analysis:

    • Check control stability (hunting, oscillation)
    • Verify setpoints match design
    • Confirm reset schedules active
    • Identify simultaneous heating/cooling

Common issues found:

  • PID tuning too aggressive (oscillation)
  • Economizer not enabled
  • Night setback not programmed
  • Outdoor air damper stuck

Seasonal Testing

Some systems require testing outside of construction season:

  • Heating: Test in winter (or simulate low OA temp)
  • Cooling: Test in summer (or simulate high OA temp)
  • Free cooling: Test economizer at shoulder season conditions

Deferred testing: Schedule within first year of operation

Issues Log and Deficiency Tracking

Maintain master issues log:

Issue #SystemDescriptionPriorityResponsibleStatusResolution
CX-001AHU-1Economizer damper stuck at minimumHighContractorClosedActuator replaced 5/12
CX-002VAV-205Airflow 20% below designMediumTABOpenDamper adjustment scheduled

Priority levels:

  • Critical: Life safety, code violation
  • High: Significant energy waste, comfort impact
  • Medium: Minor performance issue
  • Low: Documentation, cosmetic

Systems Manual

Deliverable to owner:

  1. Design narrative: System descriptions, design basis
  2. Equipment documentation: O&M manuals, shop drawings, warranties
  3. Control sequences: Detailed written sequences with points list
  4. As-built drawings: Red-lined to reflect actual installation
  5. TAB reports: Final airflow and water flow measurements
  6. Functional test reports: Results of all Cx tests
  7. Training documentation: Training session materials, video recordings

Training

Provide to facilities staff:

  1. Systems overview: How each system operates
  2. Operator interface training: BAS navigation, override procedures
  3. Preventive maintenance: Filter changes, belt inspections, seasonal tasks
  4. Troubleshooting: Common problems and solutions

Training sessions:

  • Minimum 4 hours for complex systems
  • Hands-on demonstrations
  • Provide training manual
  • Record sessions for future staff

Practical Applications

  1. New construction: Full commissioning per ASHRAE Guideline 0
  2. Existing buildings: Retro-commissioning (RCx) identifies 5-15% energy savings
  3. LEED: Enhanced commissioning (EAc3) requires additional testing
  4. Code compliance: Some jurisdictions require commissioning (California Title 24)

Related Technical Guides:

References:

  • ASHRAE Guideline 0: The Commissioning Process
  • ASHRAE Guideline 1.1: HVAC&R Technical Requirements for the Commissioning Process
  • ASHRAE Standard 202: Commissioning Process for Buildings and Systems
  • NEBB Procedural Standards for Building Systems Commissioning