Hydronic System Flushing Procedures
System Flushing Requirements
Proper flushing of hydronic systems removes construction debris, pipe scale, welding slag, flux residue, and other contaminants that can damage equipment, reduce heat transfer efficiency, and compromise system performance. System flushing is a critical commissioning activity that must be performed before equipment startup and final balancing.
Flushing Velocity Criteria
Minimum Velocity Requirements
The fundamental requirement for effective system flushing is achieving sufficient water velocity to mobilize and transport debris:
| System Type | Minimum Flushing Velocity | Target Velocity |
|---|---|---|
| Chilled water | 2.0 fps | 3.0-4.0 fps |
| Hot water | 2.0 fps | 3.0-4.0 fps |
| Condenser water | 2.5 fps | 4.0-5.0 fps |
| Large diameter mains (>6 in) | 2.5 fps | 4.0 fps |
Physics basis: The minimum 2-3 fps velocity requirement derives from the drag force needed to mobilize typical construction debris. At velocities below 2 fps, particles settle in horizontal piping and low-velocity zones, while velocities above 3 fps provide turbulent flow (Re > 4000 for typical pipe sizes) that scours pipe walls and maintains particles in suspension.
Flow Rate Calculations
To achieve target flushing velocities, calculate required flow rates:
Q = V × A × 449 gpm
Where:
- Q = flow rate (gpm)
- V = velocity (fps)
- A = pipe cross-sectional area (ft²)
- 449 = conversion factor (gpm/fps·ft²)
For circular pipes: A = π × (D/12)² / 4, where D is pipe inside diameter in inches.
Example: For 6-inch Schedule 40 pipe (ID = 6.065 in):
- A = 0.0200 ft²
- For 3.0 fps: Q = 3.0 × 0.0200 × 449 = 26.9 gpm
Flushing Procedures
Pre-Flushing Preparation
Equipment protection measures:
- Isolate all terminal equipment including coils, heat exchangers, control valves, and pumps
- Remove or bypass pump impellers (install temporary spools if necessary)
- Close automatic control valves or remove actuators
- Remove differential pressure sensing lines or close isolation valves
- Install temporary jumpers around isolation valves as needed
- Verify all strainers are clean with 20-mesh startup screens installed
Flushing Sequence
flowchart TD
A[Pre-Flush Preparation] --> B[Install Temporary Piping]
B --> C[Fill System to Operating Pressure]
C --> D[Open Flush Valves - Zone 1]
D --> E{Velocity ≥ 2 fps?}
E -->|No| F[Increase Flow Rate]
F --> E
E -->|Yes| G[Flush Until Water Clear]
G --> H[Inspect Strainer]
H --> I{Debris Present?}
I -->|Yes| J[Clean Strainer & Repeat]
J --> G
I -->|No| K[Move to Next Zone]
K --> L{All Zones Complete?}
L -->|No| D
L -->|Yes| M[Final System Flush]
M --> N[Chemical Cleaning if Required]
N --> O[Final Rinse & Fill]
O --> P[Water Quality Testing]
style E fill:#ffcccc
style I fill:#ffcccc
style L fill:#ffcccc
Systematic Flushing Process
Zone-by-zone approach:
- Divide system into flushable zones based on available flow capacity and isolation valve locations
- Begin with mains and risers flushing from highest elevation to drainage points
- Progress to branch circuits flushing individual loops sequentially
- Maintain minimum velocity continuously during flushing operations
- Monitor effluent clarity at discharge points using visual inspection
- Document each zone including flow rates, duration, and observed conditions
Flush Duration
Continue flushing each zone until:
- Discharge water runs visibly clear for minimum 15 minutes
- Strainer screens show minimal debris accumulation
- Turbidity readings stabilize below 10 NTU
- No visible particulates in collected samples
Typical duration: 30-90 minutes per zone depending on pipe size and initial contamination levels.
Chemical Cleaning Procedures
When Chemical Cleaning is Required
Chemical cleaning becomes necessary when:
- Systems contain excessive mill scale, rust, or corrosion products
- Flushing alone cannot achieve acceptable cleanliness
- Equipment manufacturers specify chemical cleaning
- Systems have been in service and require rehabilitation
Cleaning Agent Selection
| Contaminant Type | Recommended Cleaner | Concentration | Temperature |
|---|---|---|---|
| Mill scale, rust | Inhibited acid | 5-15% | 120-150°F |
| Grease, oil | Alkaline detergent | 2-5% | 140-180°F |
| Biological growth | Biocide + dispersant | Per manufacturer | 70-90°F |
| Mixed deposits | Sequential treatment | Varies | Varies |
Critical considerations:
- Material compatibility: Verify cleaner compatibility with all system materials including metals, gaskets, and coatings
- Inhibitor requirements: Use corrosion inhibitors in acid cleaning formulations to prevent base metal attack
- Neutralization: Plan for proper neutralization and disposal of spent cleaning solutions
- Contact time: Follow manufacturer recommendations for circulation time (typically 4-24 hours)
Chemical Cleaning Protocol
sequenceDiagram
participant S as System
participant C as Chemical Tank
participant M as Monitoring
participant D as Discharge
S->>C: Drain to Low Point
C->>S: Fill with Cleaning Solution
S->>S: Heat to Target Temperature
loop Circulation Period
S->>M: Monitor pH, Temperature
M->>M: Check Metal Ion Concentration
M-->>C: Add Chemicals if Needed
end
S->>D: Drain Spent Solution
D->>D: Neutralize & Dispose
S->>S: Rinse with Fresh Water (3x)
S->>M: Test Final Water Quality
Post-cleaning requirements:
- Thoroughly rinse system with fresh water until pH returns to 7.0-8.5
- Perform final flush at design velocities
- Test water chemistry for residual cleaning agents
- Add corrosion inhibitors and treatment chemicals
- Document all cleaning activities and test results
Strainer Inspection and Cleaning
Inspection Frequency
During flushing operations:
- Initial inspection: After first 15 minutes of flushing
- Subsequent inspections: Every 30 minutes until debris accumulation ceases
- Final inspection: After achieving clear discharge
Post-startup period:
- Daily inspections for first week
- Weekly inspections for first month
- Monthly inspections until debris stabilizes
Strainer Analysis
Examine collected debris for:
- Type identification: Welding slag, pipe scale, sand, metal shavings, thread sealant
- Quantity assessment: Document volume and distribution
- Source determination: Trace debris origin to identify problem areas
- Size characterization: Large particles indicate inadequate upstream filtration
Corrective actions based on findings:
- Heavy slag accumulation: Additional flushing of welded areas
- Continuous fine debris: Install finer mesh strainers temporarily
- Specific debris types: Targeted cleaning of identified problem zones
- Ongoing accumulation: Extended flushing period or chemical cleaning
Permanent Strainer Installation
After completing system flushing:
- Replace coarse startup screens (20 mesh) with permanent screens (40-60 mesh)
- Install blowdown assemblies on large strainers for online cleaning
- Verify differential pressure gauges are operational
- Set alarm points at 5-7 psid for automatic notification
- Establish routine inspection and cleaning schedule
Water Quality Testing
Post-Flush Water Analysis
Verify system cleanliness through laboratory testing:
| Parameter | Acceptance Criteria | Test Method |
|---|---|---|
| Turbidity | < 10 NTU | Nephelometric |
| Total suspended solids | < 25 mg/L | Gravimetric |
| pH | 7.0-9.5 | Electrode |
| Iron | < 1.0 mg/L | Colorimetric |
| Copper | < 0.5 mg/L | Colorimetric |
| Chlorides | < 100 mg/L | Titration |
Treatment Chemical Addition
After achieving acceptable water quality:
- Add corrosion inhibitors per manufacturer recommendations
- Adjust pH to optimal range (typically 8.0-9.0 for steel systems)
- Establish biocide program for open systems
- Add glycol if antifreeze protection required
- Document baseline water chemistry for ongoing monitoring
Documentation Requirements
Comprehensive flushing records must include:
- System schematic showing flushing zones and sequence
- Flow rates and calculated velocities for each zone
- Flushing duration and total water volume used
- Strainer inspection findings with photographs
- Water quality test results (pre and post flushing)
- Chemical cleaning procedures and material safety data
- Equipment isolation and restoration procedures
- Sign-off by commissioning authority and owner representative
This documentation becomes part of the permanent facility O&M manual and provides baseline data for future system maintenance.
Standards and References
- ASHRAE Handbook - HVAC Systems and Equipment, Chapter 43: Provides detailed guidance on water treatment and system preparation
- ASHRAE Guideline 0-2019: Commissioning process requirements including system flushing verification
- ASHRAE Guideline 3-2012: Quality installation verification of HVAC systems
- NEBB Procedural Standards: Testing, adjusting, and balancing of environmental systems
- ASTM D2777: Standard practice for water-formed deposits in closed cooling water systems
Related Topics:
- Hydronic Systems Testing overview
- Pump Performance Testing
- Flow Measurement Procedures
- Water Treatment Programs