HVAC for Natatoriums with Assembly Spectator Areas

Overview

Natatoriums with assembly spectator areas present unique HVAC challenges requiring simultaneous control of high-humidity pool environments and comfort conditioning for large variable occupant loads. Championship and competitive aquatic facilities must balance dehumidification requirements, spectator thermal comfort, IAQ demands, and energy efficiency while accommodating occupancy swings from training sessions to championship events.

Zone Separation Strategies

Competitive natatoriums require careful consideration of zone separation between the pool deck environment and spectator seating areas due to conflicting environmental requirements.

graph TB
    subgraph "Natatorium with Assembly Spectator Areas"
        A[Pool Deck Zone<br/>80-84°F DB<br/>50-60% RH] --> B[Transition Zone<br/>Pressure Control]
        B --> C[Spectator Seating<br/>68-72°F DB<br/>40-50% RH]

        D[Dedicated Pool<br/>Dehumidification Unit] --> A
        E[Spectator HVAC<br/>System] --> C

        F[Air Curtain or<br/>Physical Separation] --> B

        D --> G[Heat Recovery]
        E --> G

        H[Pool Evaporation<br/>Source] -.-> A
        I[Variable Occupancy<br/>50-2000 people] -.-> C
    end

    style A fill:#e1f5ff
    style C fill:#fff4e1
    style B fill:#f0f0f0

Combined Load Calculations

The total HVAC load for natatorium-assembly facilities requires integration of pool evaporation loads with spectator sensible and latent loads.

Pool Evaporation Rate

$$W_p = A \times F \times (p_w - p_a)$$

Where:

  • $W_p$ = evaporation rate (lb/hr)
  • $A$ = pool surface area (ft²)
  • $F$ = evaporation factor (0.1 unoccupied, 0.5 heavy use)
  • $p_w$ = saturated vapor pressure at water temperature (in. Hg)
  • $p_a$ = partial vapor pressure of room air (in. Hg)

Total Latent Load

$$Q_{latent,total} = (W_p \times 1,050) + (N \times 200)$$

Where:

  • $Q_{latent,total}$ = total latent load (Btu/hr)
  • $N$ = number of spectators
  • $200$ = average latent heat per spectator (Btu/hr)

Combined Sensible Load

$$Q_{sensible,total} = Q_{envelope} + Q_{lights} + (N \times 250) + Q_{solar}$$

Where:

  • $Q_{envelope}$ = transmission and infiltration loads (Btu/hr)
  • $Q_{lights}$ = lighting heat gain (Btu/hr)
  • $250$ = average sensible heat per spectator (Btu/hr)
  • $Q_{solar}$ = solar heat gain through glazing (Btu/hr)

Required Dehumidification Capacity

$$Q_{dehum} = \frac{Q_{latent,total}}{SHR_{target}}$$

Where $SHR_{target}$ = sensible heat ratio of dehumidification equipment (typically 0.65-0.75 for dedicated units)

System Design Approaches

Design ApproachAdvantagesDisadvantagesBest Application
Integrated Single SystemLower first cost, simplified controls, single equipment roomCompromised pool deck conditions, oversized for partial occupancy, higher operating costSmall facilities (<1,000 spectators), limited events
Separated Dual SystemsOptimized conditions for each zone, independent control, energy efficient part-loadHigher first cost, larger equipment footprint, complex coordinationChampionship facilities, frequent events, >1,000 spectators
Dedicated Pool Unit + DX for SpectatorsExcellent pool dehumidification, conventional spectator comfort, heat recovery potentialRequires coordination between systems, moderate first costMost competitive facilities, 500-2,000 spectators
Hybrid with Shared VentilationBalanced first cost, centralized air handling, zone reheat flexibilityRequires careful design, potential humidity control issuesMulti-use facilities, educational institutions

Code Requirements and Standards

ASHRAE Guidelines

ASHRAE Standard 62.1 ventilation requirements:

  • Pool deck: 0.48 cfm/ft² of pool surface area
  • Assembly seating: 5 cfm/person (assuming non-smoking)
  • Minimum air change rate: 4-6 ACH for natatorium spaces

ASHRAE Applications Handbook Chapter 6 recommendations:

  • Pool deck air temperature: 2-4°F above water temperature
  • Relative humidity: 50-60% RH (not to exceed 60%)
  • Spectator seating: 68-72°F, 40-50% RH
  • Maintain slight negative pressure (-0.02 to -0.05 in. w.g.) relative to adjacent non-pool spaces

IMC and IBC Requirements

  • Assembly occupancies (A-3, A-5) require minimum 7.5 cfm/person outdoor air
  • Pool areas classified as Group A-4 (indoor swimming pools)
  • Emergency ventilation systems required for chlorine storage areas
  • Natatoriums exceeding 300 occupant load require independent ventilation systems

Variable Occupancy Control Strategies

Championship events create occupancy loads 10-40 times greater than training sessions, requiring sophisticated control approaches.

Demand-Controlled Ventilation

  • CO₂ sensors in spectator seating zones (setpoint 800-1,000 ppm)
  • Modulating outdoor air dampers based on occupancy
  • Minimum ventilation maintained per ASHRAE 62.1

Staged Equipment Operation

  1. Base Load (Training): Pool dehumidification unit only, minimal spectator conditioning
  2. Moderate Events (Dual Meets): Base load + 50% spectator HVAC capacity
  3. Championship Events: Full system operation, all zones at design conditions
  4. Unoccupied: Setback to 75°F pool deck, dehumidification maintains 60% RH maximum

Pressure Relationship Control

Maintain proper pressure cascading to prevent moisture migration:

  • Spectator seating: +0.02 in. w.g. (positive to exterior)
  • Transition zone: neutral
  • Pool deck: -0.02 to -0.05 in. w.g. (negative to spectators)

Special Considerations for Championship Events

Pre-Event Conditioning

  • Begin spectator zone conditioning 2-4 hours before event
  • Verify pool deck at optimal conditions (prevents complaints from athletes)
  • Confirm dehumidification capacity adequate for anticipated occupancy

Peak Occupancy Management

  • Monitor relative humidity continuously (alarm if >65%)
  • Increase outdoor air ventilation as CO₂ levels rise
  • Balance spectator comfort against pool deck humidity control

Acoustic Coordination

  • Duct silencers required in spectator seating zones
  • Equipment rooms isolated from competition areas
  • Air handling units selected for NC-35 to NC-40 in seating areas

Emergency Protocols

  • Chemical spill exhaust systems independent of normal ventilation
  • Smoke evacuation coordinated with fire alarm systems
  • Manual override controls for emergency responders

Energy Recovery Opportunities

Dedicated pool dehumidification units generate substantial heat from refrigeration condensers. Heat recovery strategies include:

  • Condenser heat to pool water heating (most efficient application)
  • Hot gas reheat for supply air heating (improves dehumidification)
  • Heat recovery to spectator zone heating coils (reduces boiler load)
  • Domestic hot water preheating for shower facilities

Annual energy savings of 30-50% achievable with properly designed heat recovery compared to once-through ventilation systems.

Conclusion

HVAC systems for natatoriums with assembly spectator areas require sophisticated design balancing pool dehumidification, spectator comfort, variable occupancy, and energy efficiency. Separated systems with dedicated pool dehumidification units and independent spectator conditioning provide optimal performance for competitive facilities. Proper zone separation, combined load calculations accounting for both pool evaporation and spectator loads, and variable occupancy control strategies ensure successful operation from training sessions through championship events.

Sections

Pool Evaporation Impact on Spectator HVAC

Technical analysis of moisture migration from pool surfaces to spectator areas, covering partial pressure gradients, air barrier design, and humidity control strategies.

Chloramine Control for Spectators

Engineering strategies for protecting spectators from chloramine exposure in natatoriums through air barriers, dilution ventilation, and pressure control systems.

Spectator Area Separation in Competitive Natatoriums

Engineering strategies for effective physical and air separation between pool decks and spectator zones using pressure differentials, air curtains, and barrier systems.