HVAC Systems Encyclopedia

A comprehensive encyclopedia of heating, ventilation, and air conditioning systems

Cheese Making Process

Process Overview

Cheese manufacturing requires precise temperature and humidity control throughout multiple processing stages. Each step from milk reception through pressing generates specific thermal loads and environmental requirements that directly impact product quality, yield, and safety.

The cheese-making process involves controlled microbial and enzymatic activity that is highly temperature-dependent. HVAC systems must maintain stable conditions while handling substantial heat loads from processing equipment, pasteurization systems, and human activity in production areas.

Pasteurization Temperature Control

High-Temperature Short-Time (HTST)

Standard pasteurization parameters:

ParameterValueTolerance
Temperature72°C (161.6°F)±0.5°C
Hold Time15 seconds±0.5 sec
Flow RateDesign-dependent±2%
Regeneration Efficiency85-95%-

Heat exchanger duty calculation:

Q = ṁ × cp × ΔT

Where:
Q = Heat transfer rate (kW)
ṁ = Mass flow rate (kg/s)
cp = Specific heat of milk ≈ 3.93 kJ/(kg·K)
ΔT = Temperature rise (K)

For 10,000 L/hr milk flow (10,280 kg/hr at 1.028 kg/L):

Q = (10,280 kg/hr ÷ 3,600 s/hr) × 3.93 kJ/(kg·K) × (72 - 4)°C
Q = 2.856 kg/s × 3.93 kJ/(kg·K) × 68 K
Q = 763 kW

Cooling load with 90% regeneration:

Q_cooling = 763 kW × (1 - 0.90) = 76.3 kW

Vat Pasteurization

Lower-temperature longer-time alternative:

  • Temperature: 63°C (145°F)
  • Hold Time: 30 minutes minimum
  • Heating Rate: 2-3°C per minute maximum
  • Cooling Rate: 1-2°C per minute post-hold

Cheese Vat Temperature Control

Vat Design Parameters

Standard cheese vat specifications:

CapacityJacket AreaHeat Transfer Rate
5,000 L12 m²15-20 kW
10,000 L20 m²25-35 kW
15,000 L28 m²35-50 kW
20,000 L35 m²45-65 kW

Heating Requirements

Initial milk heating from 4°C to processing temperature:

Q_heating = m × cp × ΔT

For 10,000 L vat:
m = 10,280 kg
cp = 3.93 kJ/(kg·K)
ΔT = 32°C - 4°C = 28 K

Q_heating = 10,280 kg × 3.93 kJ/(kg·K) × 28 K
Q_heating = 1,131,158 kJ = 314 kWh

With 60-minute heat-up time:

Required heating capacity = 314 kWh ÷ 1 hr = 314 kW

Including 25% safety factor: 393 kW

Mesophilic Cheese Production

Temperature ranges for Cheddar, Gouda, Monterey Jack:

Process StageTemperatureDurationControl Tolerance
Milk Addition31-32°C-±0.5°C
Culture Addition31°C30-45 min±0.5°C
Rennet Addition31°C-±0.3°C
Coagulation31°C30-45 min±0.3°C
Cutting31°C15-30 min±0.5°C
Cooking32-38°C30-60 min±0.5°C
Drainage38°CVariable±1.0°C

Cooking rate control:

Heating rate = 0.5 to 1.0°C per 5 minutes

For Cheddar (31°C to 38°C):
Time = 7°C ÷ (1°C per 5 min) = 35 minutes minimum

Thermophilic Cheese Production

Temperature ranges for Swiss, Parmesan, Provolone:

Process StageTemperatureDurationControl Tolerance
Milk Addition32-34°C-±0.5°C
Culture Addition32-34°C15-30 min±0.5°C
Rennet Addition32-34°C-±0.3°C
Coagulation32-34°C20-30 min±0.3°C
Cutting32-34°C10-20 min±0.5°C
Cooking48-54°C45-90 min±0.5°C
Drainage52-54°CVariable±1.0°C

High-temperature cooking for Swiss-type cheese may reach 54-56°C with controlled ramp rates of 1°C per 3-5 minutes.

Curd Processing Temperatures

Cheddarization Process

Specific to Cheddar and related varieties:

StageTemperaturepH TargetDuration
Draining38°C6.4-6.2-
Matting38-39°C6.2-5.81-2 hrs
Milling37-38°C5.8-5.4-
Salting35-36°C5.3-5.210-20 min
Hooping32-35°C5.2-5.1-

Room temperature control during Cheddarization:

Ambient temperature: 22-26°C
Relative humidity: 80-90%
Air velocity: <0.3 m/s at curd surface

Heat loss from exposed curd:

Q_loss = h × A × (T_curd - T_ambient)

Where:
h = Convective heat transfer coefficient ≈ 10 W/(m²·K)
A = Exposed surface area (m²)

For 100 m² exposed curd surface:

Q_loss = 10 W/(m²·K) × 100 m² × (38°C - 24°C)
Q_loss = 14,000 W = 14 kW

Pasta Filata Process

For Mozzarella and similar stretched-curd cheeses:

ParameterValueNotes
Stretching Water Temp75-85°CLow-moisture varieties
Stretching Water Temp65-75°CHigh-moisture varieties
Curd pH for Stretching5.2-5.4Critical for texture
Stretching Duration3-8 minutesVariety-dependent
Post-Stretch Temp54-60°CBefore forming

Stretching water heating load:

For 500 L/hr water flow at 80°C (from 15°C supply):

Q_water = ṁ × cp × ΔT
Q_water = (500 kg/hr ÷ 3,600 s/hr) × 4.186 kJ/(kg·K) × 65 K
Q_water = 37.7 kW continuous load

Cooling and Pressing Requirements

Immediate Post-Vat Cooling

Curd cooling after drainage:

Cheese TypeInitial TempTarget TempCooling Rate
Fresh Cheese32-35°C4-8°C2-4 hrs
Soft-Ripened30-32°C10-12°C2-3 hrs
Semi-Hard35-38°C12-15°C3-4 hrs
Hard Cheese38-40°C10-14°C6-12 hrs

Cooling load calculation for pressed cheese:

For 1,000 kg curd mass cooled from 35°C to 12°C in 4 hours:

Q_cooling = m × cp × ΔT ÷ t

Cheese specific heat ≈ 3.1 kJ/(kg·K)

Q_cooling = 1,000 kg × 3.1 kJ/(kg·K) × 23 K ÷ (4 × 3,600 s)
Q_cooling = 4.98 kW average

Peak load at start of cooling cycle approaches 2.5× average load.

Pressing Systems

Hydraulic and pneumatic press specifications:

Press TypePressure RangeTemperature ControlCooling Method
Hydraulic1-5 barRoom temperatureAmbient
Pneumatic0.5-4 barRoom temperatureAmbient
Vacuum-0.8 to -0.95 bar10-18°CRefrigerated room

Pressing room environmental conditions:

Temperature: 12-18°C
Relative Humidity: 75-85%
Air Changes: 4-6 ACH
Room Pressurization: Neutral to slightly positive

Heat generation during pressing:

Q_press = Work done on curd + Metabolic heat

Metabolic heat ≈ 0.8-1.2 W/kg curd
Mechanical work minimal for pressing loads

For 5,000 kg curd in pressing room:
Q_metabolic = 5,000 kg × 1.0 W/kg = 5.0 kW

Brine Bath Refrigeration

Brine System Design

Standard brine concentrations and properties:

ParameterValueNotes
Salt Concentration18-23% by weightMost common
Operating Temperature8-14°CVariety-dependent
Calcium Addition0.5-1.5% CaCl₂Prevents calcium loss
pH5.0-5.5Controlled
Density1,140-1,170 kg/m³At 10°C
Specific Heat3.54 kJ/(kg·K)At 20% NaCl

Brine Bath Capacity

Typical brine bath sizes for different production scales:

Production RateBath VolumeRefrigeration Load
1,000 kg/day5,000 L8-12 kW
5,000 kg/day15,000 L25-40 kW
10,000 kg/day30,000 L50-75 kW
20,000 kg/day50,000 L90-130 kW

Heat Load Components

Total brine refrigeration load:

Q_total = Q_cheese + Q_infiltration + Q_evaporation + Q_ambient

Q_cheese = Heat removed from warm cheese entering brine
Q_infiltration = Heat gain from room air and water vapor
Q_evaporation = Latent heat from surface evaporation
Q_ambient = Conduction through tank walls and piping

Heat removal from cheese:

For 1,000 kg/hr cheese entering at 18°C, cooled to 12°C:

Q_cheese = ṁ × cp × ΔT
Q_cheese = (1,000 kg ÷ 3,600 s) × 3.1 kJ/(kg·K) × 6 K
Q_cheese = 5.17 kW

Evaporative losses from open brine surface:

Q_evap = hfg × ṁ_evap

Where:
hfg = Latent heat of vaporization ≈ 2,450 kJ/kg
ṁ_evap = Evaporation rate (kg/s)

For 20 m² surface area at 12°C brine, 18°C room:
Evaporation ≈ 0.3 kg/(hr·m²) = 6 kg/hr = 0.00167 kg/s

Q_evap = 2,450 kJ/kg × 0.00167 kg/s = 4.1 kW

Brine Circulation

Circulation pump specifications:

Flow rate: 3-5 tank volumes per hour
Head: 10-20 m depending on piping layout
Temperature rise across pump: <0.5°C

For 15,000 L tank with 4 vol/hr circulation:

Flow rate = 15 m³/hr × 4 = 60 m³/hr
Mass flow = 60 m³/hr × 1,150 kg/m³ = 69,000 kg/hr

Pump power ≈ 3-5 kW
Heat addition from pumping ≈ 2.5-4.0 kW

Process Room HVAC Design

Temperature Control Zones

Multiple temperature zones required in cheese plant:

AreaTemperatureRHAir ChangesPressurization
Milk Receiving4-8°C80-85%6-8 ACHNeutral
Vat Room22-26°C70-80%8-12 ACHPositive 15-25 Pa
Cheddarization22-26°C80-90%6-10 ACHPositive 10-20 Pa
Pressing Room12-18°C75-85%4-6 ACHNeutral
Brining Room10-14°C85-90%4-6 ACHNeutral
Packaging4-8°C75-80%8-10 ACHPositive 20-30 Pa

Vat Room Design

Critical HVAC parameters for vat room:

Sensible heat load sources:
- Equipment (vats, pumps, conveyors): 50-80 W/m²
- Lighting (LED): 8-12 W/m²
- Occupants (moderate activity): 130 W/person sensible
- Infiltration: 10-15 W/m² floor area

For 500 m² vat room with 8 vats, 12 occupants:

Q_equipment = 500 m² × 65 W/m² = 32.5 kW
Q_lighting = 500 m² × 10 W/m² = 5.0 kW
Q_occupants = 12 persons × 130 W = 1.56 kW
Q_infiltration = 500 m² × 12 W/m² = 6.0 kW

Q_sensible_total = 45.1 kW

Latent heat load:

Q_latent sources:
- Occupants: 12 persons × 70 W/person = 0.84 kW
- Open vats: Varies by stage
- Cleaning operations: 15-25 W/m²

Q_latent_total ≈ 8-12 kW

Ventilation Requirements

Air change rates based on activity and contaminant generation:

Minimum outdoor air: 0.5 L/(s·m²) floor area

For 500 m² vat room:
Outdoor air = 500 m² × 0.5 L/(s·m²) = 250 L/s = 900 m³/hr

At 10 ACH with 4 m ceiling height:

Room volume = 500 m² × 4 m = 2,000 m³
Total air flow = 2,000 m³ × 10 hr⁻¹ = 20,000 m³/hr

Outdoor air fraction = 900 ÷ 20,000 = 4.5%
Recirculated air = 95.5%

Equipment Heat Loads

Cheese Vat Heat Dissipation

Heat dissipated to room from vat operations:

OperationHeat to RoomDurationNotes
Agitation Motor2-5 kWIntermittentVariable speed
Cutting Assembly1-3 kW15-30 minOnce per batch
Pump Operation3-8 kWIntermittentTransfer operations
Jacket Losses2-4 kWContinuousDepends on insulation

Single vat total heat dissipation:

Average continuous load per vat ≈ 4-8 kW
Peak load during active processing ≈ 12-18 kW

For 8-vat room:
Average load = 8 vats × 6 kW = 48 kW
Peak load = 8 vats × 15 kW = 120 kW

Design for 70% peak: 84 kW

Curd Processing Equipment

Heat loads from downstream equipment:

EquipmentPower InputHeat to RoomDuty Cycle
Curd Mill15-30 kW12-25 kW60-80%
Curd Conveyor5-10 kW4-8 kW70-90%
Block Former10-20 kW8-16 kW80-100%
Stretch Cooker40-80 kW25-50 kW70-90%
Packaging Line20-40 kW15-30 kW80-100%

Pump Heat Addition

Heat generated by various pumps in cheese plant:

Milk transfer pumps: 5-15 kW per pump
Curd/whey pumps: 3-10 kW per pump
Brine circulation: 3-5 kW per pump
CIP pumps: 10-30 kW per pump

Heat addition to fluid ≈ 80-90% of motor power
Heat to room ≈ 10-20% of motor power (motor inefficiency)

For positive displacement pump transferring milk:

Power = (P × Q) ÷ η

Where:
P = Pressure increase (Pa)
Q = Flow rate (m³/s)
η = Pump efficiency (0.70-0.85)

Example: 20 m³/hr at 300 kPa, η = 0.75

Power = (300,000 Pa × 20 m³/hr ÷ 3,600 s/hr) ÷ 0.75
Power = 2,222 W = 2.22 kW input

Heat to product: 2.22 kW × 0.85 = 1.89 kW
Heat to room: 2.22 kW × 0.15 = 0.33 kW

Humidity Control During Processing

Moisture Management

Relative humidity targets prevent excessive curd drying:

Curd processing areas: 75-85% RH
Pressing rooms: 75-85% RH
Brining rooms: 85-90% RH
Packaging areas: 70-80% RH

Dehumidification load calculation:

Moisture removal rate = ṁ_air × (ω_inlet - ω_outlet)

Where:
ṁ_air = Air mass flow rate (kg/s)
ω = Humidity ratio (kg water/kg dry air)

For pressing room at 15°C:

Target: 80% RH (ω = 0.00856 kg/kg)
Infiltration air: 30°C, 60% RH (ω = 0.0162 kg/kg)
Infiltration rate: 1,000 m³/hr = 1,200 kg/hr dry air

Moisture to remove:
ṁ_moisture = (1,200 kg/hr ÷ 3,600 s/hr) × (0.0162 - 0.00856)
ṁ_moisture = 0.00255 kg/s = 9.2 kg/hr

Latent load = 9.2 kg/hr × 2,450 kJ/kg = 6.25 kW

Humidification Requirements

Winter conditions may require humidification:

Outdoor air: -5°C, 70% RH (ω = 0.0019 kg/kg)
Target: 24°C, 80% RH (ω = 0.0151 kg/kg)
Outdoor air flow: 1,000 m³/hr at 24°C = 1,165 kg/hr dry air

Moisture addition required:
ṁ_add = (1,165 kg/hr ÷ 3,600 s/hr) × (0.0151 - 0.0019)
ṁ_add = 0.00427 kg/s = 15.4 kg/hr

Steam requirement (if steam humidification):
15.4 kg/hr steam at 2,450 kJ/kg = 10.5 kW

Condensation Prevention

Critical surfaces requiring condensation control:

  • Stainless steel vat exteriors
  • Cold piping and valves
  • Refrigerated room walls and doors
  • Observation windows

Minimum surface temperature to prevent condensation:

T_surface_min = T_dewpoint + 2°C safety margin

At 24°C, 80% RH:
T_dewpoint = 20.4°C
T_surface_min = 22.4°C

Insulation requirement for 4°C milk line in 24°C room:
R_required = (T_room - T_surface) ÷ q"

Target q" = 15 W/m² (reasonable heat flux)

R_required = (24 - 22.4) K ÷ 15 W/m² = 0.107 m²·K/W

For polyurethane insulation (k = 0.025 W/(m·K)):
Thickness = 0.107 × 0.025 = 2.7 mm minimum

Practical minimum: 25 mm (1 inch) for mechanical protection

Sanitation Temperature Requirements

Clean-in-Place (CIP) Systems

Multi-stage CIP cycle temperatures:

StageTemperatureDurationPurpose
Pre-RinseAmbient-40°C3-5 minGross soil removal
Caustic Wash75-85°C10-20 minFat and protein removal
Intermediate Rinse40-60°C3-5 minCaustic removal
Acid Wash65-75°C10-15 minMineral scale removal
Final RinseAmbient-40°C3-5 minAcid removal
Sanitizer20-40°C5-10 minMicrobial control

CIP Heat Loads

Heating requirements for CIP solutions:

Tank capacity: 2,000 L per circuit
Caustic solution: 1.5-3.0% NaOH
Acid solution: 1.0-2.0% HNO₃

Heat to raise 2,000 L from 20°C to 80°C:

Q = m × cp × ΔT
m = 2,000 kg (assuming water properties)
cp = 4.186 kJ/(kg·K)
ΔT = 60 K

Q = 2,000 × 4.186 × 60 = 502,320 kJ = 139.5 kWh

With 45-minute heat-up time:
Power required = 139.5 kWh ÷ 0.75 hr = 186 kW

Including 20% heat losses: 223 kW heating capacity

Recovery and reuse reduces heating load:

Caustic solution reused 4-6 cycles before replacement
Temperature drop per cycle: 5-10°C
Reheat load per cycle: 42-84 kJ/kg = 23-47 kWh per cycle

Hot Water Generation

Daily hot water requirements for cheese plant:

UseTemperatureDaily VolumePeak Flow
CIP Systems75-85°C50-80 L/kg cheese10-20 m³/hr
Equipment Sanitizing82-85°C20-30 L/kg cheese5-10 m³/hr
Floor/Wall Cleaning60-70°C15-25 L/kg cheese5-8 m³/hr
Hand Washing40-45°C5-10 L/kg cheese2-4 m³/hr

For 10,000 kg/day cheese production:

Total hot water demand:
CIP: 10,000 kg × 65 L/kg = 650,000 L/day at 80°C
Sanitizing: 10,000 kg × 25 L/kg = 250,000 L/day at 82°C
Cleaning: 10,000 kg × 20 L/kg = 200,000 L/day at 65°C
Hand washing: 10,000 kg × 7.5 L/kg = 75,000 L/day at 43°C

Total volume: 1,175,000 L/day = 1,175 m³/day

Water heating load (from 10°C supply):

Q_daily = Σ(m × cp × ΔT)

Q_CIP = 650,000 kg × 4.186 kJ/(kg·K) × 70 K = 190,578 MJ
Q_sanitize = 250,000 kg × 4.186 kJ/(kg·K) × 72 K = 75,350 MJ
Q_clean = 200,000 kg × 4.186 kJ/(kg·K) × 55 K = 46,046 MJ
Q_handwash = 75,000 kg × 4.186 kJ/(kg·K) × 33 K = 10,360 MJ

Q_total = 322,334 MJ/day = 89,537 kWh/day

Average continuous load = 89,537 kWh ÷ 24 hr = 3,731 kW

Peak capacity requirement (20% of daily in 2 hours):
Peak = 89,537 kWh × 0.20 ÷ 2 hr = 8,954 kW

Steam Requirements

Process steam generation for direct and indirect heating:

Total plant steam load components:
- Vat heating: 300-500 kW
- Pasteurization: 50-100 kW (after regeneration)
- CIP heating: 200-400 kW
- Hot water generation: 3,500-4,500 kW
- Building heating (winter): 500-1,000 kW
- Safety factor: 20%

Total design capacity = 5,500 kW × 1.20 = 6,600 kW

Steam at 6 bar gauge (447 kPa, 159°C):
hfg = 2,085 kJ/kg

Required steam flow = 6,600 kW ÷ 2,085 kJ/kg = 3.17 kg/s
= 11,394 kg/hr = 11.4 tonnes/hr

Boiler capacity: 15,000 kg/hr (allows for peak loads)

Equipment Specifications

Refrigeration System Design

Central glycol system for process cooling:

ParameterSpecificationNotes
RefrigerantR-404A, R-507A, NH₃Facility-dependent
Glycol TypePropylene glycolFood-grade
Glycol Concentration30-40% by volume-18°C freeze protection
Supply Temperature-2 to 2°CProcess-dependent
Return Temperature8 to 12°CDesign ΔT = 10 K
System Pressure4-6 barDistribution pressure

Total refrigeration capacity:

Component loads for 10,000 kg/day plant:
- Milk cooling (reception): 80-120 kW
- Post-pasteurization cooling: 60-90 kW
- Vat cooling (makeup): 40-60 kW
- Curd cooling: 30-50 kW
- Brine bath: 50-75 kW
- Process room HVAC: 100-150 kW
- Cold storage: 80-120 kW
- Safety factor: 25%

Total = 565 kW × 1.25 = 706 kW

Installed capacity: 800 kW (multiple compressors)

Pump Specifications

Process pumps for cheese manufacturing:

ServiceTypeMaterialsSanitary Standard
Milk TransferCentrifugal316L SS3-A, EHEDG
Curd TransferLobe316L SS3-A
Whey TransferCentrifugal316L SS3-A
Brine CirculationCentrifugal316L SS, TitaniumFood-grade
CIP SupplyCentrifugal316L SS3-A

Air Handling Unit Specifications

Dedicated AHU for vat room (500 m² example):

Supply Air Flow: 20,000 m³/hr
Outdoor Air: 900 m³/hr (4.5%)
Total Cooling: 60 kW (45 kW sensible, 15 kW latent)
Total Heating: 40 kW (winter)
Supply Fan: 7.5 kW with VFD
Return Fan: 5.5 kW with VFD
Filters: MERV 13 minimum
Cooling Coil: Chilled water, 6/12°C
Heating Coil: Hot water, 80/60°C or steam
Humidifier: Steam injection or ultrasonic

Supply duct velocities:

Main ducts: 8-12 m/s
Branch ducts: 6-10 m/s
Terminal diffusers: 2-4 m/s at discharge

Controls Integration

Building automation system (BAS) integration points:

  • Vat temperature control (±0.3°C precision)
  • Room temperature and humidity monitoring
  • Glycol supply temperature reset
  • Demand-based ventilation control
  • CIP temperature verification
  • Brine concentration and temperature
  • Refrigeration system optimization
  • Energy metering and trending

Control sequences coordinate HVAC with process requirements to maintain product quality while minimizing energy consumption.


File Location: /Users/evgenygantman/Documents/github/gantmane/hvac/content/refrigeration-systems/food-processing-refrigeration/dairy-processing/cheese-manufacturing/cheese-making-process/_index.md

This comprehensive technical content covers all critical HVAC and refrigeration aspects of cheese manufacturing processes for HVAC professionals designing or maintaining cheese production facilities.