Schematic Design Phase
The schematic design (SD) phase establishes fundamental HVAC system concepts and confirms design feasibility. This phase translates owner requirements into preliminary technical solutions, establishes spatial requirements, and provides cost and energy consumption estimates for decision-making.
Phase Objectives
The schematic design phase accomplishes:
- System concept selection based on building type, owner requirements, and site constraints
- Preliminary load calculations establishing system capacity requirements
- Major equipment identification defining primary system components
- Space allocation for mechanical rooms, shafts, and distribution paths
- Cost estimation providing budget validation (±20-30% accuracy)
- Energy analysis comparing system alternatives and establishing performance baselines
System Concept Development
System Selection Criteria
System concept selection evaluates:
Building Characteristics:
- Occupancy type and schedule
- Space function and layout
- Floor-to-floor height limitations
- Ceiling plenum availability
- Architectural constraints
Performance Requirements:
- Thermal comfort criteria
- Indoor air quality targets
- Humidity control needs
- Acoustical limitations
- Operational flexibility
Zoning Considerations:
- Thermal zone requirements
- Exposure variations (perimeter vs. interior)
- Schedule diversity
- Space pressurization needs
- Simultaneous heating and cooling loads
Primary System Types
All-Air Systems:
- Variable air volume (VAV) with reheat
- Constant volume multizone
- Dual duct systems
- Single zone constant volume
Application: Office buildings, schools, retail spaces requiring centralized control and high ventilation rates.
Air-Water Systems:
- Four-pipe fan coil units
- Chilled beams (active and passive)
- Water source heat pumps
- Radiators with ventilation systems
Application: Hotels, residential buildings, perimeter zones requiring individual control.
All-Water Systems:
- Hydronic radiant panels
- Baseboard radiation
- Unit heaters
- Trench heaters
Application: Industrial spaces, warehouses, perimeter heating applications.
Refrigerant-Based Systems:
- Variable refrigerant flow (VRF)
- Packaged terminal units
- Split systems
- Rooftop units
Application: Tenant spaces, renovations, buildings without central plant capacity.
Distribution System Concepts
Central vs. Distributed:
Central plant systems concentrate equipment in mechanical rooms, distributing conditioned air or water throughout the building. Advantages include maintenance access, equipment efficiency, and acoustical isolation. Disadvantages include distribution losses, vertical shaft requirements, and single-point failure risk.
Distributed systems locate equipment throughout the building near served spaces. Advantages include reduced distribution, simplified zoning, and redundancy. Disadvantages include maintenance access challenges, space consumption, and acoustical concerns.
Horizontal Distribution:
Establish routing concepts for:
- Supply and return air ducts or piping
- Corridor ceiling vs. plenum distribution
- Above-ceiling vs. raised-floor pathways
- Coordination with structural systems
- Integration with electrical and plumbing systems
Vertical Distribution:
Define shaft requirements for:
- Main supply and return risers
- Equipment access and maintenance
- Future capacity expansion
- Fire and smoke separation
- Acoustic isolation between floors
Preliminary Load Calculations
Calculation Methodology
Schematic design load calculations use simplified methods providing ±15-25% accuracy:
Block Load Approach:
Calculate loads for entire building or major zones rather than individual spaces. This method establishes overall system capacity without detailed room-by-room analysis.
Cooling Load Components:
External loads:
- Envelope transmission: Q = U × A × CLTD
- Solar radiation through glazing: Q = A × SHGC × SC × CLF
- Infiltration: Q = 1.1 × CFM × ΔT + 4840 × CFM × Δω
Internal loads:
- Occupant sensible: Q = N × 250 BTU/hr (typical office)
- Occupant latent: Q = N × 200 BTU/hr (typical office)
- Lighting: Q = W × 3.41 × BF × CLF
- Equipment: Q = W × 3.41 × Usage Factor × CLF
- Miscellaneous sources
Ventilation:
- Outdoor air sensible: Q = 1.1 × CFM × (To - Ti)
- Outdoor air latent: Q = 4840 × CFM × (ωo - ωi)
Heating Load Components:
Envelope losses:
- Transmission: Q = U × A × ΔT
- Infiltration: Q = 1.1 × CFM × ΔT
Ventilation heating:
- Outdoor air heating: Q = 1.1 × CFM × (Ti - To)
Humidification (if required):
- Moisture addition: Q = CFM × Δω × 4840 BTU/lb-water
Design Conditions
Outdoor Conditions:
Reference ASHRAE climatic design data:
- Summer: 0.4%, 1%, or 2% dry-bulb and mean coincident wet-bulb
- Winter: 99.6% or 99% dry-bulb
- Humidity ratios at design conditions
Selection depends on system reliability requirements and operational cost considerations.
Indoor Conditions:
Establish target conditions:
- Summer: 75°F ± 2°F, 50% RH ± 10%
- Winter: 70°F ± 2°F, 30% RH minimum
- Special requirements for specific space types
Diversity Factors:
Apply appropriate diversity to account for non-simultaneous operation:
- Occupancy: 0.7-0.9 (office buildings)
- Lighting: 0.8-1.0 (depends on control strategy)
- Equipment: 0.5-0.8 (depends on space type)
- System-level diversity: 0.85-0.95
Load Calculation Software
Utilize simplified calculation tools:
- ASHRAE block load calculator
- eQuest preliminary design mode
- Carrier HAP quick load
- Trane TRACE 700 schematic module
- RTS method spreadsheets
Equipment Space Allocation
Mechanical Room Sizing
Central Equipment Spaces:
Estimate floor area requirements:
Boiler rooms:
- 1.5-2.5 SF per MBH input capacity
- Minimum clearances: 3 ft sides, 6 ft front, 4 ft rear
- Combustion air openings
- Fuel supply access
Chiller rooms:
- 2.0-3.0 SF per ton cooling capacity
- Tube pull space: 1.5 × tube length
- Maintenance access around equipment
- Refrigerant monitoring and ventilation
Air handling unit rooms:
- 3-4 times AHU footprint for access and ductwork
- Minimum ceiling height: equipment height + 3 ft
- Filter and coil access clearances
- Ductwork and piping transitions
Pump rooms:
- 50-100 SF per pump (depending on size)
- Clearances for motor removal
- Pipe and valve access
- Future expansion capacity
Vertical Shafts:
Size shafts for:
- Main supply risers: 0.3-0.5 SF per 1000 CFM
- Main return risers: 0.3-0.5 SF per 1000 CFM
- Hydronic risers: 0.1-0.2 SF per 100 GPM
- Access doors every 3-4 floors
- Fire damper locations
Equipment Locations:
Evaluate placement options:
Rooftop:
- Advantages: Outdoor air access, sound isolation, no building space consumption
- Disadvantages: Weather exposure, structural reinforcement, aesthetic impact
Basement:
- Advantages: Structural support, sound isolation, outdoor air via wells
- Disadvantages: Flooding risk, excavation cost, natural light limitation
Intermediate floors:
- Advantages: Reduced distribution distances, stacked shaft alignment
- Disadvantages: Floor space consumption, structural loading, noise transmission
Outdoor pads:
- Advantages: Easy access, no building space, simple installation
- Disadvantages: Weather exposure, security concerns, visual impact, noise
Major Equipment Selection
Heating Equipment
Boilers:
Preliminary selection based on:
- Fuel type: natural gas, fuel oil, electric
- Configuration: fire-tube, water-tube, condensing
- Capacity: total heating load × 1.15-1.25 safety factor
- Efficiency: AFUE 80-95% (non-condensing), 90-98% (condensing)
- Quantity: redundancy requirements (N+1 or 2×50%)
Typical sizing:
- Input capacity: output ÷ efficiency
- Footprint: estimate from manufacturer data
- Flue requirements: diameter based on input capacity
Heat Pumps:
Air-source heat pumps:
- Capacity: match cooling load, verify heating capacity at design conditions
- COP heating: 2.5-3.5 at 47°F, 1.5-2.5 at 17°F
- Supplemental heat: electric resistance or fossil fuel backup
Water-source heat pumps:
- Capacity: 0.5-2.0 tons per unit (varies by application)
- Loop temperature: 60-90°F operating range
- Boiler and cooling tower: size for simultaneous loads
Cooling Equipment
Chillers:
Selection parameters:
- Capacity: total cooling load × 1.10-1.20 safety factor
- Efficiency: 0.5-0.65 kW/ton (water-cooled), 0.9-1.2 kW/ton (air-cooled)
- Configuration: air-cooled, water-cooled, evaporative-cooled
- Compressor type: centrifugal, screw, scroll
- Refrigerant: R-134a, R-513A, R-1233zd(E), R-515B
Preliminary sizing:
- Tons = sensible load + latent load + duct gain + safety factor
- GPM chilled water = (tons × 24) ÷ (ΔT × 500)
- Condenser water GPM = (tons × 30) ÷ (ΔT × 500)
Cooling Towers:
Estimate parameters:
- Capacity: chiller heat rejection + compressor power
- Approach: 7-10°F (counterflow), 5-7°F (crossflow)
- Range: 10-20°F (typically 10-15°F)
- GPM: match condenser water flow
- Type: induced draft, forced draft, crossflow, counterflow
Air Handling Equipment
Air Handling Units:
Size based on:
- Airflow: CFM = sensible load ÷ (1.1 × ΔT)
- Supply temperature: 55-58°F (cooling), 95-105°F (heating)
- Face velocity: 400-500 FPM (coils), 500 FPM (filters)
- Pressure drop: 2-4 in. w.g. (internal), 2-6 in. w.g. (external)
Component sizing:
- Cooling coil: 4-6 rows, 8-12 fins per inch
- Heating coil: 2-4 rows, 8-10 fins per inch
- Filters: MERV 8-13, 300-500 FPM face velocity
- Fan: forward-curved, backward-inclined, or airfoil
Package Units:
Rooftop units:
- Capacity: 3-150 tons (standard sizes)
- Efficiency: 10-14 IEER (air-cooled)
- Configuration: single-zone or VAV
- Supply air: constant or variable volume
Split systems:
- Capacity: 1.5-5 tons (typical residential/light commercial)
- SEER: 13-21 (cooling efficiency)
- HSPF: 8-10 (heating efficiency)
- Configuration: single-stage, two-stage, variable-speed
Pump Selection
Chilled Water Pumps:
Preliminary sizing:
- Flow rate: GPM = (tons × 24) ÷ (ΔT × 500)
- Temperature difference: 10-14°F (12°F typical)
- Head: estimate 50-100 ft for distribution + equipment drops
- Control: variable speed with pressure sensor
Condenser Water Pumps:
Sizing parameters:
- Flow rate: GPM = (tons × 30) ÷ (ΔT × 500)
- Temperature rise: 10-20°F (10°F typical)
- Head: estimate 40-80 ft including tower lift
- Control: constant speed or variable speed
Heating Water Pumps:
Design values:
- Flow rate: GPM = (MBH × 500) ÷ (ΔT × 500)
- Temperature drop: 20-40°F (20°F typical high-temp, 10°F low-temp)
- Head: estimate 40-100 ft for distribution + coils
- Control: variable speed with differential pressure sensor
Budget Estimation
Cost Estimating Methods
Unit Cost Method:
Apply costs per building area:
- Office buildings: $8-$15/SF
- Healthcare: $25-$40/SF
- Schools: $10-$18/SF
- Retail: $6-$12/SF
- Laboratories: $40-$80/SF
Ranges reflect system complexity, building size, and regional variations.
System Component Method:
Estimate major component costs:
Heating equipment:
- Boilers: $15-$30 per MBH input
- Heat pumps: $1,200-$2,000 per ton
Cooling equipment:
- Air-cooled chillers: $800-$1,200 per ton
- Water-cooled chillers: $600-$1,000 per ton
- Cooling towers: $150-$300 per ton
- Package rooftop units: $1,000-$1,500 per ton
Air distribution:
- Air handling units: $3-$6 per CFM
- Ductwork: $8-$15 per SF served
- Diffusers and grilles: $100-$300 each
Hydronic systems:
- Pumps: $200-$500 per HP
- Piping: $20-$40 per linear foot (installed)
- Terminal units: $800-$1,500 per unit
Controls:
- DDC system: $2-$5 per SF
- VAV boxes with controls: $1,500-$2,500 each
Contingency Factors:
Include appropriate contingencies:
- Design contingency: 15-25% (schematic phase)
- Escalation: 3-5% per year to construction midpoint
- Geographic adjustment: regional cost indices
Cost Documentation
Prepare preliminary cost estimate including:
- Basis of estimate (building area, system type, equipment counts)
- Unit costs and quantities
- Subtotals by system category
- Contingencies and markups
- Total construction cost
- Comparison to budget allocation
Preliminary Energy Analysis
Analysis Objectives
Schematic phase energy analysis establishes:
- Baseline energy consumption and cost
- System alternative comparison
- Energy code compliance path
- Owner’s sustainability goals feasibility
Modeling Methodology
Simplified Analysis:
Use bin method or degree-day calculations:
- Annual heating load: HDD × 24 × UA × efficiency factor
- Annual cooling load: CDD × 24 × UA × efficiency factor
- Equipment energy: loads ÷ equipment efficiency × operating hours
Simulation Tools:
Employ preliminary energy modeling:
- eQuest quick mode
- Trace 700 early design
- IES VE conceptual design module
- Carrier HAP energy analysis
Input minimal detail:
- Building envelope U-values and SHGC
- System types and efficiencies
- Occupancy schedules
- Lighting power density
- Equipment power density
- HVAC system operating parameters
System Comparison
Performance Metrics:
Compare alternatives using:
- Annual energy consumption (kBTU/SF-yr)
- Energy Use Intensity (EUI)
- Energy cost ($/SF-yr)
- Peak demand (W/SF)
- Source energy consumption
- Carbon emissions (lb CO₂/SF-yr)
System Alternatives:
Evaluate options:
Base case: code-minimum system
- Standard efficiency equipment
- Minimum insulation and glazing performance
- Required ventilation rates
Alternative 1: improved efficiency
- High-efficiency equipment (10-20% improvement)
- Enhanced envelope performance
- Heat recovery systems
Alternative 2: advanced systems
- Variable refrigerant flow
- Dedicated outdoor air systems
- Energy recovery ventilation
- Demand-controlled ventilation
Alternative 3: renewable integration
- Ground-source heat pumps
- Solar thermal domestic hot water
- Photovoltaic offset
- Combined heat and power
Life Cycle Cost Analysis
Economic Evaluation:
Perform simplified LCC analysis:
First cost:
- Equipment and installation
- Design and commissioning
- Incremental envelope improvements
Operating costs:
- Annual energy consumption × utility rates
- Maintenance cost estimates
- Equipment replacement reserves
Analysis period: 15-25 years
Economic metrics:
- Simple payback period
- Net present value (NPV)
- Internal rate of return (IRR)
- Savings-to-investment ratio (SIR)
Discount rate: 3-5% real (excluding inflation)
Deliverables
Drawing Requirements
Produce schematic design drawings:
Mechanical Plans (1/16" or 1/8" scale):
- Major equipment locations and sizes
- Primary ductwork and piping mains
- Mechanical room layouts
- Vertical shaft locations
- Outdoor equipment placement
- Coordination with architectural and structural systems
Riser Diagrams:
- Vertical distribution concept
- Main supply and return routes
- Equipment connections
- Control zones
Equipment Schedules:
- Major equipment list with preliminary capacities
- Approximate dimensions and weights
- Utility requirements (electrical, gas, water)
- Performance specifications
Technical Documentation
Prepare written descriptions:
Basis of Design Narrative:
- System selection rationale
- Design criteria and parameters
- Load calculation summary
- Equipment selection basis
- Energy analysis results
- Code compliance approach
Specifications Outline:
- Division 23 sections list
- Performance criteria
- Quality standards referenced
- Installation requirements overview
Cost Estimate:
- Component-level cost breakdown
- Comparison to budget
- Value engineering opportunities identified
Owner Review Package
Compile submittal including:
- Design drawings
- Basis of design narrative
- Load calculation summary
- Equipment schedules
- Cost estimate
- Energy analysis comparison
- Design alternatives evaluation
- Project schedule implications
Coordination Requirements
Architectural Integration
Coordinate with architectural design:
- Ceiling heights and mechanical clearances
- Shaft locations and sizes
- Mechanical room locations
- Equipment access and egress
- Louver and grille locations
- Roof penetrations and equipment placement
- Acoustical criteria
Structural Coordination
Provide structural team with:
- Equipment weights and locations
- Mechanical room live loads
- Roof equipment support requirements
- Pipe and duct support loads
- Seismic requirements
- Vibration isolation details
Electrical Coordination
Define electrical requirements:
- Voltage and phase for major equipment
- Transformer and switchgear capacity
- Emergency power requirements
- Control power needs
- Lighting and receptacle coordination in mechanical spaces
Plumbing Coordination
Coordinate with plumbing design:
- Domestic water heating method
- Condensate drainage
- Makeup water connections
- Backflow prevention
- Floor drains in mechanical rooms
Design Review and Approval
Internal Review
Conduct design team reviews:
- Load calculation verification
- System concept appropriateness
- Equipment sizing reasonableness
- Cost estimate accuracy
- Constructability assessment
- Code compliance verification
Owner Review Meeting
Present design concept:
- System description and rationale
- Preliminary drawings explanation
- Cost and schedule implications
- Energy performance projections
- Design alternatives discussion
- Outstanding decisions requiring owner input
Authority Having Jurisdiction
Engage code officials:
- Preliminary code review meeting
- Ventilation rate confirmation
- Energy code compliance path
- Fire and life safety coordination
- Special system requirements
Obtain feedback before proceeding to design development.
Schematic Design Checklist
Verify completion of:
- Owner requirements documented and incorporated
- System concept selected and approved
- Preliminary load calculations completed
- Major equipment identified and sized
- Mechanical room locations and sizes established
- Shaft and distribution routing concepts defined
- Cost estimate prepared and within budget
- Energy analysis comparing alternatives completed
- Drawings at appropriate level of detail
- Basis of design narrative prepared
- Coordination with other disciplines completed
- Owner review and approval obtained
- Design schedule maintained
The schematic design phase establishes HVAC system fundamentals that guide subsequent design development and construction documentation. Thorough concept evaluation and stakeholder alignment during this phase prevent costly revisions later in the project delivery process.
Sections
Schematic Design Deliverables
Components
- Basis Of Design Narrative
- Load Calculation Preliminary
- System Selection Evaluation
- Conceptual Floor Plans
- Single Line Diagrams
- Equipment Layout Preliminary
- Space Requirements Mechanical Rooms
- Equipment Capacity Summary
- Energy Analysis Preliminary
- Cost Estimate Schematic Rom
- Schematic Design Report
Sd Meetings Reviews
Components
- Sd Kickoff Meeting
- Owner Design Criteria Review
- Architectural Coordination Sd
- Structural Coordination Sd
- Electrical Coordination Sd
- Plumbing Coordination Sd
- Code Review Preliminary
- Sustainability Goals Review
- Sd Presentation Owner
- Sd Approval Authorization
Sd Documentation
Components
- Design Intent Drawings
- Conceptual System Layouts
- Preliminary Equipment Sizing
- Utility Requirements
- Architectural Space Requirements
- Structural Load Requirements
- Electrical Service Requirements