Proposal Phase
The proposal phase establishes the foundation for the HVAC design project by defining scope, assembling the team, and establishing contractual parameters. This phase transforms client needs into a structured approach for delivering mechanical engineering services.
Project Understanding
Initial Client Contact
The proposal process begins with understanding the client’s objectives and project requirements:
- Review Request for Proposal (RFP) or Request for Qualifications (RFQ) documents
- Identify stated requirements for HVAC systems
- Determine building type, occupancy, and programmatic needs
- Understand project delivery method (design-bid-build, design-build, CM-at-risk)
- Clarify sustainability goals (LEED, WELL, net-zero targets)
- Identify code jurisdiction and applicable standards
Site Visit and Assessment
When possible, conduct site reconnaissance to evaluate:
- Existing conditions for renovation projects
- Space availability for mechanical equipment
- Access for equipment installation and replacement
- Utility availability and capacity
- Environmental constraints
- Adjacent building impacts
Clarification Questions
Develop and submit clarifying questions to address:
- Ambiguities in the RFP
- Missing information needed for accurate scope development
- Coordination requirements with other disciplines
- Owner-furnished equipment or systems
- Phasing requirements
- Commissioning expectations
Scope Development
Defining Design Services
Establish clear boundaries for HVAC engineering services:
Basic HVAC Design Services:
- Heating system design
- Cooling system design
- Ventilation system design
- Exhaust system design
- Air distribution systems
- Hydronic piping systems
- Equipment selection and specifications
- Control system specifications (points list and sequences)
- Energy code compliance analysis
- Construction documents preparation
Additional Services (if applicable):
- Energy modeling and analysis
- Computational fluid dynamics (CFD) analysis
- Life cycle cost analysis
- Commissioning support beyond basic design review
- LEED or other certification documentation
- Cost estimating
- Value engineering studies
- Construction administration beyond standard site visits
- Record drawing preparation
- Operations and maintenance manual development
Assumptions and Clarifications
Document assumptions that define scope boundaries:
- Design basis (outdoor and indoor design conditions)
- Codes and standards to be applied
- Number of design iterations included
- Coordination meetings participation
- Drawing deliverable quantities and formats
- Submittal review turnaround times
- Site visit frequency during construction
- Client-provided information (architectural drawings, structural capacity, existing equipment data)
Exclusions
Clearly state services not included in the base scope:
- Plumbing and fire protection design (unless specifically included)
- Building automation system programming
- Testing, adjusting, and balancing services
- Commissioning authority services
- Utility coordination beyond preliminary capacity verification
- Permit expediting services
- Shop drawing preparation
- As-built drawing preparation
Fee Proposal Development
Fee Structures
Select appropriate fee structure based on project characteristics:
Lump Sum Fee:
- Fixed fee for defined scope
- Appropriate when scope is well-defined
- Includes contingency for minor scope changes
- Risk allocated to design professional
Hourly Fee (Not-to-Exceed):
- Time-based billing with upper limit
- Appropriate for renovation work with unknowns
- Requires detailed labor category breakdown
- Client approval for exceeding cap
Percentage of Construction Cost:
- Fee based on percentage of mechanical construction cost
- Common for institutional and government projects
- Typical range: 4-8% depending on complexity
- Requires construction cost basis agreement
Unit Cost Fee:
- Fee per square foot or per system
- Appropriate for repetitive building types
- Establishes clear cost basis
- Requires detailed unit definition
Cost Estimation
Develop accurate fee estimates based on:
Labor Hours Estimation:
- Break down by design phase (SD, DD, CD, CA)
- Allocate hours by labor category (principal, project manager, engineer, designer, technician)
- Include coordination meetings and reviews
- Factor in revision cycles
- Add project management overhead
Typical Hour Distribution by Phase:
| Phase | Percentage of Total Hours |
|---|---|
| Schematic Design | 15-20% |
| Design Development | 25-30% |
| Construction Documents | 40-50% |
| Construction Administration | 10-15% |
Direct Costs:
- Printing and reproduction
- Travel expenses for site visits
- Specialized consultants (commissioning, testing, energy modeling)
- Software licenses for analysis
- Permit fees (if design professional is responsible)
Fee Letter Format
Structure fee proposals with clear organization:
- Project understanding summary
- Scope of services by phase
- Fee breakdown by phase
- Additional services available
- Assumptions and clarifications
- Exclusions
- Payment schedule
- Term and validity period
Qualifications Presentation
Firm Experience
Demonstrate relevant capability through:
Project Examples:
- Similar building types and sizes
- Comparable mechanical system complexity
- Relevant delivery methods
- Geographic experience in same climate zone
- Code jurisdiction familiarity
Technical Capabilities:
- In-house design software and analysis tools
- Quality control procedures
- BIM capabilities and LOD standards
- Sustainable design experience
- Specialized system expertise
Client References:
- Recent projects with contact information
- Repeat clients demonstrating satisfaction
- Projects with same project delivery method
- Similar scale and complexity
Professional Credentials
Highlight qualifications that demonstrate competency:
- Professional Engineering (PE) licenses by state
- LEED Accredited Professionals (LEED AP)
- Certified Commissioning Authority (CxA)
- ASHRAE member involvement
- Continuing education commitment
- Awards and recognition
Quality Assurance Program
Describe internal quality control procedures:
- Multi-level drawing review process
- Calculation verification protocols
- Code compliance checklists
- Coordination review procedures
- Specification review process
- Lessons learned documentation
Team Organization
Project Roles and Responsibilities
Define team structure with clear accountability:
Principal-in-Charge:
- Overall project responsibility
- Client relationship management
- Contract negotiations
- Final design approval
- Quality assurance oversight
Project Manager:
- Day-to-day project coordination
- Schedule management
- Budget tracking
- Communication with architect and owner
- Deliverable coordination
- Issue resolution
Lead Mechanical Engineer:
- Technical design leadership
- System selection and design
- Load calculations and equipment sizing
- Energy code compliance
- Specification development
- Construction administration support
Design Engineers:
- System layout and design
- Duct and pipe sizing calculations
- Equipment schedule preparation
- Detail development
- Submittal review
CADD/BIM Technicians:
- Drawing production in Revit or AutoCAD
- Model coordination with other disciplines
- Detail drafting
- Drawing quality control
Specifications Writer:
- Technical specifications preparation
- Product selection coordination
- Specification section coordination
- Addenda preparation
Subconsultants
Identify required specialty consultants:
- Commissioning Authority (for LEED or complex projects)
- Testing, Adjusting, and Balancing (TAB) contractor
- Energy modeling consultant
- CFD analysis specialist
- Acoustical consultant (for noise-sensitive applications)
- Controls contractor (for complex BAS)
Staffing Plan
Demonstrate adequate resource allocation:
- Identify personnel by name and role
- Show percentage allocation by phase
- Demonstrate availability for project duration
- Indicate backup personnel for key roles
- Show subconsultant team integration
Schedule Development
Phase Duration Estimates
Establish realistic timeframes for each design phase:
Schematic Design (SD):
- Duration: 2-4 weeks typical
- Deliverables: System concepts, preliminary equipment sizing, space requirements
- Review cycles: 1-2 iterations
Design Development (DD):
- Duration: 4-6 weeks typical
- Deliverables: Refined system design, equipment schedules, outline specifications
- Review cycles: 1-2 iterations with owner and authorities having jurisdiction (AHJ)
Construction Documents (CD):
- Duration: 8-12 weeks typical
- Deliverables: Complete drawings, specifications, calculations
- Review cycles: 50%, 90%, 100% milestones
- Permitting submittal preparation
Bidding/Negotiation:
- Duration: 2-4 weeks
- Support services: RFI responses, addenda preparation, pre-bid meetings
Construction Administration (CA):
- Duration: Matches construction schedule (6-18 months typical)
- Services: Submittal review, RFI responses, site visits, punch list review
Critical Path Activities
Identify schedule dependencies that affect HVAC design:
- Architectural programming and space planning (affects load calculations)
- Structural capacity verification (for rooftop equipment)
- Electrical service sizing coordination
- Equipment lead time verification (for long-lead items)
- Authority having jurisdiction (AHJ) review cycles
- Client approval milestones
- Commissioning plan development
Milestone Schedule
Present key deliverable dates in tabular format:
| Milestone | Duration | Cumulative Time |
|---|---|---|
| Project Kickoff | - | Week 0 |
| SD Submission | 3 weeks | Week 3 |
| SD Review Complete | 1 week | Week 4 |
| DD Submission | 5 weeks | Week 9 |
| DD Review Complete | 1 week | Week 10 |
| 50% CD Submission | 4 weeks | Week 14 |
| 90% CD Submission | 4 weeks | Week 18 |
| 100% CD Submission | 2 weeks | Week 20 |
| Permit Submission | 1 week | Week 21 |
Schedule Assumptions
Document factors that affect timeline accuracy:
- Client review and approval durations
- Information receipt from other disciplines
- Concurrent review (not sequential) with other trades
- Number of review iterations per phase
- AHJ review time not included in design schedule
- Adequate client decision-making timeframes
- Availability of existing building information
Risk Assessment and Mitigation
Technical Risks
Identify potential design challenges:
- Inadequate space for equipment
- Insufficient utility capacity
- Unknown existing conditions (renovation projects)
- Aggressive energy targets with limited budget
- Phasing complexity during occupied renovation
- Fast-track schedule compressing design phases
Mitigation Strategies
Propose approaches to minimize risks:
- Early equipment space planning and coordination
- Preliminary utility coordination meetings
- Investigative site visits and equipment inspections
- Value engineering sessions to align budget with performance goals
- Detailed phasing plan development
- Increased coordination frequency for compressed schedules
Proposal Submission
Submission Requirements
Ensure compliance with RFP requirements:
- Specified number of copies (hard copy and electronic)
- Page limits or formatting requirements
- Required certifications or affidavits
- Insurance certificates
- Disadvantaged Business Enterprise (DBE) or Minority Business Enterprise (MBE) participation plans
- Submittal deadline and delivery method
Proposal Components
Organize submission for clarity and completeness:
- Cover letter summarizing qualifications and approach
- Project understanding and approach
- Scope of services
- Project team and qualifications
- Relevant project experience
- Schedule
- Fee proposal (separate sealed envelope if required)
- Required forms and certifications
- Insurance documentation
- Client references
Interview Preparation
If shortlisted, prepare for selection interview:
- Develop presentation materials (typically 20-30 minutes)
- Assemble interview team (key personnel only)
- Prepare responses to likely technical questions
- Anticipate questions about project approach
- Bring project examples and supporting materials
- Rehearse presentation for timing and clarity
Contract Negotiation
Standard Contract Forms
Understand common agreement structures:
- AIA B101 (Standard Form of Agreement Between Owner and Architect) with architect subconsultant agreement
- EJCDC E-500 (Agreement Between Owner and Engineer)
- ConsensusDocs 240 (Standard Agreement Between Owner and Engineer)
- Client-specific agreement forms
Key Contract Terms
Negotiate critical provisions:
Scope Changes:
- Additional services authorization process
- Change order procedures
- Fee adjustment methodology
Standard of Care:
- Professional standard of care language
- Limitation of liability provisions
- Statute of limitations
Payment Terms:
- Monthly invoicing based on percentage complete or phase completion
- Retainage (typically 0-5%)
- Payment timeline (net 30 days typical)
- Interest on late payments
Insurance Requirements:
- Professional liability limits (typically $1-2M per occurrence)
- General liability coverage
- Workers compensation
- Automobile liability
Intellectual Property:
- Ownership of instruments of service
- License for owner use
- Limitations on reuse without compensation
Post-Award Activities
Project Kickoff
Initiate project with clear communication:
- Schedule kickoff meeting with full design team
- Establish communication protocols and meeting schedules
- Confirm scope, schedule, and budget
- Identify outstanding information needs
- Review quality assurance procedures
- Establish document control procedures
Design Phase Planning
Organize work for efficient execution:
- Develop detailed design schedule with milestones
- Assign tasks to team members
- Establish coordination meeting frequency
- Set up project file structure and BIM environment
- Initiate background research and code review
- Begin preliminary load calculations
The proposal phase sets expectations and establishes the contractual framework for successful HVAC design project delivery. Thorough scope definition, realistic scheduling, and clear communication of qualifications position the project for success from inception.
Sections
Proposal Development
Components
- Request For Proposal Analysis
- Scope Of Work Definition
- Fee Proposal Development
- Hourly Rate Structure
- Lump Sum Fee Estimation
- Percentage Of Construction Cost
- Staffing Plan Development
- Principal In Charge Assignment
- Project Manager Assignment
- Design Team Composition
- Subconsultant Coordination
- Proposal Schedule Development
Client Meetings
Components
- Initial Client Interview
- Project Goals Understanding
- Budget Constraints Discussion
- Schedule Requirements Review
- Site Visit Initial
- Existing Conditions Assessment
- Stakeholder Identification
- Decision Making Process
- Communication Protocols
Proposal Submission
Components
- Proposal Formatting
- Firm Qualifications Statement
- Relevant Project Experience
- Staff Resumes Qualifications
- Project Approach Methodology
- Fee Breakdown Schedule
- Terms Conditions
- Insurance Certification
- Professional Licensure Documentation