Construction Bidding Phase
The construction bidding phase translates design documents into construction contracts, establishing the framework for project execution. Proper bid phase management ensures qualified contractors, competitive pricing, and clear contractual terms for HVAC system installation.
Bid Document Preparation
Bid Package Contents
Complete HVAC bid packages include:
Contract Documents:
- Agreement form
- General conditions
- Supplementary conditions
- HVAC specifications (Division 23)
Drawing Set:
- Mechanical plans
- Equipment schedules
- Details and sections
- Control diagrams
Bid Forms:
- Base bid form
- Alternate pricing
- Unit prices
- Allowances
Specification Sections
Typical HVAC specification divisions:
| Section | Content |
|---|---|
| 230500 | Common work results |
| 230593 | Testing, adjusting, balancing |
| 230900 | Instrumentation and control |
| 232100 | Hydronic piping |
| 233100 | HVAC ducts and casings |
| 233600 | Air terminal units |
| 237200 | Air handling units |
| 238100 | Decentralized HVAC |
Addenda Process
Issue addenda to clarify or modify bid documents:
- Formal distribution to all bidders
- Track addendum acknowledgment
- Deadline for pre-bid changes
- Impact on bid due date
Pre-Bid Activities
Bidder Qualification
Evaluate contractor capabilities:
Financial:
- Bonding capacity
- Insurance coverage
- Financial statements
- Credit references
Technical:
- Similar project experience
- Staff qualifications
- Equipment capabilities
- Safety record
Administrative:
- License verification
- Reference checks
- Legal standing
- Workforce availability
Pre-Bid Meeting
Mandatory or optional meeting to:
- Review project scope
- Answer contractor questions
- Site visit and access
- Schedule clarification
- Document interpretations
Record and distribute meeting minutes to all bidders.
Request for Information (RFI)
Pre-bid RFIs address document ambiguities:
- Contractor submits written question
- Engineer/architect reviews
- Response via addendum (to all bidders)
- Deadline for RFI submission
Bid Submission
Bid Requirements
Format:
- Sealed envelope/electronic
- Completed bid form
- Addenda acknowledgment
- Bid bond (typically 5%)
Schedule:
- Submission deadline (exact time)
- Public opening (competitive)
- Evaluation period
- Award notification
Bid Security
Bid bonds guarantee contractor commitment:
- 5-10% of bid amount typical
- AIA Document A310 form
- Forfeiture upon withdrawal
- Released after contract execution
Bid Evaluation
Responsive Bid Criteria
Verify bids meet requirements:
- All forms complete
- Addenda acknowledged
- Proper signatures
- Bond included
- On-time submission
Technical Evaluation
Review for compliance:
- Equipment meets specifications
- Alternates properly priced
- Unit prices reasonable
- Qualifications acceptable
Price Analysis
| Evaluation Item | Consideration |
|---|---|
| Base bid | Primary comparison |
| Alternates | Add/deduct as planned |
| Unit prices | Compare to estimates |
| Allowances | Standard amounts |
| Total value | Complete comparison |
Lowest Responsible Bidder
Award typically to lowest responsible bidder:
Responsible Criteria:
- Technical capability
- Financial capacity
- Past performance
- Legal compliance
- Available resources
Contract Award
Notice of Award
Formal notification includes:
- Bid amount accepted
- Contract time
- Required submittals
- Performance/payment bonds
- Insurance certificates
- Contract execution deadline
Contract Execution
Complete contract documents:
- Signed agreement
- Performance bond (100%)
- Payment bond (100%)
- Insurance certificates
- Notice to proceed
Unsuccessful Bidders
Notify unsuccessful bidders:
- Release bid bonds
- Provide bid tabulation (if public)
- Answer debriefing requests (if applicable)
Special Considerations
Prequalification
For complex HVAC systems:
- Prequalify before bidding
- Limit bidders to qualified list
- Detailed capability assessment
- Reduces bid evaluation burden
Negotiated Procurement
Alternatives to competitive bid:
- Design-build delivery
- Construction management
- Qualified contractor negotiation
- Best-value selection
Public vs. Private
Public Projects:
- Strict competitive bidding
- Lowest responsible bidder
- Transparent process
- Defined protest procedures
Private Projects:
- More flexibility
- Relationship considerations
- Negotiation possible
- Faster process potential
The construction bidding phase establishes critical contractor relationships and contractual terms that govern project execution, with proper procedures ensuring fair competition and qualified contractor selection.
Sections
Pre-Bid Procedures
Comprehensive guide to HVAC pre-bid procedures including invitation to bid, bid document preparation, pre-bid meetings, site visits, RFI process, bid security requirements, and contractor prequalification for mechanical construction projects
Bid Evaluation
Comprehensive HVAC bid evaluation procedures including responsiveness review, contractor qualification verification, scope completeness analysis, alternates assessment, value engineering proposals, and systematic contractor selection criteria for mechanical construction projects
Addenda Process
Comprehensive guide to HVAC construction addenda including preparation procedures, timing requirements, distribution methods, clarification responses, specification modifications, drawing revisions, and documentation practices during the bidding phase
Bid Award Procedures
Comprehensive HVAC bid award procedures including award notification, contract execution, notice to proceed, performance bonds, payment bonds, insurance requirements, and contract document assembly for mechanical construction projects