HVAC Systems Encyclopedia

A comprehensive encyclopedia of heating, ventilation, and air conditioning systems

Commissioning Integration in HVAC Project Delivery

Commissioning (Cx) integrates quality-focused processes throughout project delivery to verify HVAC systems meet owner requirements and design intent. Effective commissioning requires early planning, continuous verification, and systematic documentation from programming through occupancy.

Commissioning Process Overview

ASHRAE Guideline 0-2019 defines commissioning as a quality-focused process for achieving, verifying, and documenting performance of systems to meet Owner’s Project Requirements (OPR) within project budget and schedule.

Commissioning Phases

graph LR
    A[Pre-Design] --> B[Design]
    B --> C[Construction]
    C --> D[Acceptance]
    D --> E[Post-Occupancy]

    A1[OPR Development] -.-> A
    B1[BOD Documentation] -.-> B
    C1[Installation Verification] -.-> C
    D1[Functional Testing] -.-> D
    E1[Systems Manual] -.-> E

Pre-design phase:

  • Develop Owner’s Project Requirements (OPR)
  • Establish commissioning scope and budget
  • Select commissioning authority (CxA)

Design phase:

  • Create Basis of Design (BOD)
  • Develop commissioning plan
  • Review design submissions for OPR compliance
  • Develop preliminary test procedures

Construction phase:

  • Verify installation per construction documents
  • Witness factory and startup testing
  • Execute functional performance tests
  • Document deficiencies and verify corrections

Acceptance phase:

  • Complete final testing and verification
  • Compile systems manual with O&M documentation
  • Provide owner training
  • Issue final commissioning report

Post-occupancy phase (ongoing commissioning):

  • Monitor performance 10-12 months post-occupancy
  • Verify seasonal operation
  • Optimize control sequences
  • Re-train facilities staff as needed

Owner’s Project Requirements (OPR)

The OPR documents owner objectives, criteria, and expectations for project performance—the foundation for all design and commissioning activities.

OPR Content Requirements

Project goals and objectives:

  • Occupancy type and operational hours
  • Critical performance requirements (temperature, humidity, air quality)
  • Energy efficiency targets (EUI, LEED certification level)
  • Maintainability and operational simplicity preferences

HVAC system requirements:

Space conditioning criteria:

Space TypeTemperature RangeHumidity RangeVentilation RateSpecial Requirements
Office70-76°F (21-24°C)30-60% RH17 CFM/personNone
Laboratory68-75°F (20-24°C)30-60% RH6-12 ACHFume hood exhaust
Data Center64-80°F (18-27°C)40-60% RHVariableN+1 redundancy
Operating Room68-73°F (20-23°C)30-60% RH20 ACH minimumHEPA filtration, positive pressure

System reliability and redundancy:

  • Uptime requirements (%, hours downtime allowable)
  • Redundancy level (N, N+1, 2N)
  • Backup power requirements
  • Maintenance windows and scheduling constraints

Energy and sustainability:

  • Energy budget (Btu/ft²-yr or kWh/m²-yr)
  • Renewable energy percentage targets
  • Water conservation goals
  • Refrigerant environmental impact limits (GWP, ODP)

Measurement and verification:

  • Metering granularity (whole building, system, equipment)
  • Monitoring and trending requirements
  • Performance metrics and reporting frequency

OPR Development Process

Stakeholder workshops:

  1. Operations staff: Maintenance capabilities, training needs, spare parts access
  2. Facilities management: Energy budgets, operational costs, system lifecycle
  3. End users: Comfort expectations, noise tolerance, control preferences
  4. Executive leadership: Capital budget, operational budget, sustainability commitments

OPR documentation format:

  • Narrative requirements organized by system
  • Quantitative criteria with measurable metrics
  • Prioritization (must have vs. nice to have)
  • Budget constraints and lifecycle cost considerations

OPR updates:

  • Review at design milestones (SD, DD, CD) for owner approval
  • Document changes and reasons
  • Maintain version control and change log

Basis of Design (BOD)

The BOD documents design assumptions, criteria, and methodology demonstrating how design satisfies OPR requirements.

BOD Content Structure

Design assumptions:

  • Climate data (design temperatures, humidity)
  • Occupancy density and schedules
  • Lighting and equipment heat gains
  • Infiltration and envelope performance

Load calculations:

  • Methodology (ASHRAE heat balance method, equivalent temperature difference)
  • Peak heating and cooling loads by zone
  • Diversity factors and safety factors applied
  • Load calculation software and inputs

System selection rationale:

Primary HVAC system:

$$\text{System EUI} = \frac{\sum(\text{Equipment kW} \times \text{Operating Hours})}{1000 \times \text{Floor Area}}$$

Comparison matrix evaluating alternatives:

System TypeFirst CostOperating CostEnergy UseMaintenanceFootprint
VAV w/ reheatBaselineBaselineBaselineMediumCompact
DOAS + radiant+25%-15%-20%LowLarger
Chilled beam+15%-10%-12%LowCompact
Fan coils-10%+5%+8%HighDistributed

Equipment sizing and selection:

  • Nameplate capacities with margin analysis
  • Part-load performance considerations
  • Efficiency ratings (EER, COP, IPLV)
  • Manufacturer selection criteria

Control system design:

  • Control architecture (centralized vs. distributed)
  • Sequence of operations narrative
  • Sensor locations and accuracy requirements
  • User interface and access levels

Compliance documentation:

  • Energy code compliance (ASHRAE 90.1, IECC)
  • Ventilation code compliance (ASHRAE 62.1, IMC)
  • Special code requirements (healthcare, laboratory)

BOD Review Process

Design milestone reviews:

  • 30% SD: Confirm system selection aligns with OPR
  • 60% DD: Verify sizing, performance specifications
  • 90% CD: Check details, controls, specifications complete
  • 100% CD: Final compliance verification

CxA review focus:

  • OPR alignment verification
  • Design assumptions reasonability
  • Equipment performance specifications adequacy
  • Controllability and testability of final design
  • Maintainability and operational complexity

Design issues register:

  • Document discrepancies between OPR and BOD
  • Track resolution through design iterations
  • Obtain owner decisions on conflicts (performance vs. cost)

Commissioning Plan

The commissioning plan defines the scope, schedule, responsibilities, and procedures governing commissioning activities.

Commissioning Scope Definition

Systems included in commissioning:

Full commissioning (testing and verification):

  • Central heating and cooling plants
  • Air handling units and distribution systems
  • Terminal equipment and controls
  • Building automation system
  • Metering and monitoring systems

Limited commissioning (verification only):

  • Domestic water heating systems
  • Plumbing systems
  • Fire protection systems (separate testing authority)

Excluded systems:

  • Site utilities (outside building envelope)
  • Temporary HVAC systems
  • Owner-furnished equipment (unless specified)

Commissioning Schedule

Integration with project schedule:

Project PhaseCommissioning ActivitiesDurationDependencies
DesignBOD review, test plan development2-4 weeks per milestoneDesign submissions
SubmittalsEquipment review, coordinationOngoingSubmittal log updates
InstallationSite observations, installation checksWeeklyConstruction progress
StartupWitness startup, initial testing2-4 weeksSubstantial completion
Functional TestingExecute test procedures4-8 weeksStartup complete
TrainingO&M training sessions1-2 weeksSystems operational

Critical path considerations:

  • BAS programming completion enables control testing
  • Chiller startup requires cooling tower and pumps operational
  • Air balance prerequisite to final functional tests
  • Seasonal testing (heating requires winter conditions)

Roles and Responsibilities

Owner responsibilities:

  • Provide OPR and approve updates
  • Review and approve commissioning plan
  • Attend commissioning meetings
  • Participate in training sessions
  • Accept commissioned systems

Commissioning authority (CxA) responsibilities:

  • Develop commissioning plan and test procedures
  • Review design submissions for OPR compliance
  • Attend construction meetings
  • Witness startup and conduct functional tests
  • Compile systems manual and final report

Design engineer responsibilities:

  • Develop BOD aligned with OPR
  • Support CxA design reviews
  • Develop detailed control sequences
  • Respond to commissioning observations
  • Attend functional testing

Contractor responsibilities:

  • Install systems per construction documents
  • Provide startup services and witness tests
  • Correct deficiencies identified during commissioning
  • Provide O&M documentation
  • Support training activities

Test agent responsibilities (if separate from CxA):

  • Perform air and water balancing
  • Document flow and performance measurements
  • Correct deficiencies within scope
  • Provide certified TAB reports

Construction Phase Commissioning

Active verification during construction ensures systems installed correctly and capable of testing.

Installation Verification

Prefunctional checklists: Equipment-specific verification forms confirming:

  • Model number matches specifications
  • Installation orientation and location correct
  • Connections (electrical, piping, ductwork) complete
  • Safety devices and interlocks functional
  • Controls wiring and power verified
  • Insulation and labeling complete

Sampling methodology:

For repetitive equipment (VAV boxes, fan coils):

$$\text{Sample Size} = \max\left(10%\text{ of population}, 10\text{ units}\right)$$

Example: 75 VAV boxes → sample 10 units minimum

Site observation frequency:

  • Weekly during rough-in phase
  • Bi-weekly during equipment setting
  • Daily during startup and testing phases

Startup Procedures

Manufacturer startup services:

  • Central plant equipment (chillers, boilers, large AHUs)
  • Specialized equipment (energy recovery, building automation)
  • Commissioned by factory-trained technicians
  • Documented on manufacturer startup forms

Contractor startup services:

  • Standard equipment (pumps, small fans, unit heaters)
  • Executed per manufacturer instructions
  • Verified by commissioning authority
  • Documented on contractor startup reports

Startup verification criteria:

  • Equipment runs without abnormal noise or vibration
  • Operating parameters within manufacturer limits
  • Safety devices test correctly
  • Control sequences execute as designed

Functional Performance Testing

Functional tests verify integrated system performance under actual and simulated load conditions.

Test procedure components:

  1. Prerequisites: Conditions required before test (TAB complete, controls programmed)
  2. Equipment required: Instrumentation and tools needed
  3. Procedures: Step-by-step test execution instructions
  4. Expected results: Performance criteria defining pass/fail
  5. Actual results: Documented observations and measurements
  6. Deficiencies: Issues identified requiring correction

Example functional test: VAV terminal unit with reheat

Test StepActionExpected ResultAcceptance Criteria
1Verify minimum airflowBAS displays min flow setpoint±10% of design minimum
2Command zone to heatingDamper modulates to min position, reheat valve opensDamper ≤ min + 5%, valve > 0%
3Satisfy zone temperatureReheat valve closesValve = 0%
4Command zone to coolingDamper modulates toward maxDamper position increases
5Verify maximum airflowBAS displays max flow setpoint±10% of design maximum
6Simulate space temp above setpointDamper remains at max, reheat locked outDamper = max, valve = 0%

Testing sequence strategy:

  1. Component-level testing (individual equipment)
  2. System-level testing (integrated operation)
  3. Interface testing (inter-system coordination)
  4. Seasonal testing (modes not available during initial testing)

Deficiency Management

Deficiency classification:

  • Critical: System cannot operate, safety issue, code violation
  • Major: Performance significantly degraded, repeated failures
  • Minor: Performance slightly impaired, cosmetic issues

Deficiency resolution workflow:

graph TD
    A[Identify Deficiency] --> B[Document in Log]
    B --> C[Assign Responsibility]
    C --> D[Contractor Correction]
    D --> E[CxA Verification]
    E --> F{Resolved?}
    F -->|Yes| G[Close Deficiency]
    F -->|No| H[Escalate to Owner]
    H --> I[Determine Path Forward]
    I --> C

Resolution tracking metrics:

  • Deficiency age (days open)
  • Responsible party performance
  • Recurring deficiency patterns
  • Outstanding critical issues preventing acceptance

Commissioning Deliverables

Final commissioning report contents:

  • Executive summary of commissioning process and outcomes
  • OPR and BOD documentation with final revisions
  • Commissioning plan and schedule
  • Installation verification checklists
  • Functional test procedures and results
  • Deficiency log with resolution documentation
  • Training records and attendee lists
  • Recommendations for ongoing commissioning

Systems manual:

  • Equipment documentation (submittals, O&M manuals)
  • As-built drawings (architectural, mechanical, electrical, controls)
  • Sequence of operations (final, as-programmed)
  • Testing and balancing reports
  • Warranty documentation
  • Recommended maintenance schedules
  • Spare parts lists and sources

Training deliverables:

  • Training curriculum and materials
  • Hands-on demonstrations completed
  • Competency verification (if required)
  • Video recordings of training sessions

Comprehensive commissioning integration ensures HVAC systems perform as intended, reducing energy consumption by 10-20%, improving comfort complaints by 50-80%, and extending equipment life through proper operation and maintenance.


Subsections provide detailed guidance on OPR Development, Basis of Design Documentation, Commissioning Plan Creation, and Construction Phase Commissioning Procedures.

Sections

Owner's Project Requirements (OPR) Documentation

Comprehensive guide to developing Owner's Project Requirements for HVAC commissioning per ASHRAE Guideline 0, including performance criteria, operational needs, and documentation structure.

Basis of Design in HVAC Commissioning

Comprehensive guide to Basis of Design documentation structure, BOD-OPR relationships, design assumptions, system descriptions, and ASHRAE commissioning requirements.

Commissioning Plan Development and Implementation

Comprehensive framework for HVAC commissioning plans covering phases from pre-design through post-occupancy, deliverables, team responsibilities, and workflow management.

Construction Phase Commissioning: FPT & Verification

Construction phase commissioning procedures including installation verification, functional performance testing, startup requirements, and deficiency resolution per ASHRAE Guideline 1.1.